Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Paris
3 days agoCammy
4 days agoKristine
21 days agoMickie
1 months agoOretha
4 days agoPaola
16 days agoTegan
17 days agoSoledad
21 days agoLina
1 months agoMollie
1 months agoLorriane
14 days agoJerrod
18 days agoKerry
1 months agoPearline
2 months agoLina
2 months ago