PMI Exam PMI-SP Topic 9 Question 86 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 86
Topic #: 9
[All PMI-SP Questions]

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Paris
3 days ago
Well, if Activity B takes 8 days, I guess we'll just have to put Activity H on hold until the cows come home - so that's D) Zero days, right?
upvoted 0 times
...
Cammy
4 days ago
Wait, does this mean I can take a four-day vacation while we wait for Activity H to start? Sign me up for that delay!
upvoted 0 times
...
Kristine
21 days ago
This question is making my head spin! I'm going to go with the answer that sounds the most reasonable - C) Four days. Fingers crossed that's the right choice!
upvoted 0 times
...
Mickie
1 months ago
Oh no, my project management skills are being tested! Let me see... If Activity B is delayed, that pushes out Activity H. I'll go with C) Four days, but I'm crossing my fingers!
upvoted 0 times
Oretha
4 days ago
Let's hope it's not too big of a delay!
upvoted 0 times
...
Paola
16 days ago
I believe it's D) Zero days.
upvoted 0 times
...
Tegan
17 days ago
I'm not sure, maybe it's A) Three days?
upvoted 0 times
...
Soledad
21 days ago
I think it's C) Four days too.
upvoted 0 times
...
...
Lina
1 months ago
That makes sense, thanks for explaining!
upvoted 0 times
...
Mollie
1 months ago
This is a tricky one! If Activity B is delayed by 3 days, that means the entire critical path is delayed by 3 days. So, the answer has to be C) Four days.
upvoted 0 times
Lorriane
14 days ago
Yes, that makes sense. So the answer is C) Four days.
upvoted 0 times
...
Jerrod
18 days ago
I think you're right, if Activity B is delayed by 3 days, then Activity H can be delayed by 4 days.
upvoted 0 times
...
...
Kerry
1 months ago
Hmm, let me think about this. If Activity B takes 8 days instead of 5, that would delay the start of Activity H. The question is asking how long can we delay Activity H, so I'm going to go with C) Four days.
upvoted 0 times
...
Pearline
2 months ago
I disagree, I believe the answer is C) Four days because Activity H is dependent on Activity B.
upvoted 0 times
...
Lina
2 months ago
I think the answer is A) Three days.
upvoted 0 times
...