Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Herman
5 months agoMatthew
5 months agoShonda
5 months agoVernice
5 months agoNieves
6 months agoBenedict
6 months agoTimothy
6 months agoMoon
6 months agoRobt
6 months agoLucia
6 months agoMary
6 months agoSarina
6 months agoVilma
7 months agoErasmo
7 months agoParis
11 months agoCammy
11 months agoCarman
10 months agoCecily
10 months agoRupert
10 months agoJennifer
11 months agoKristine
12 months agoDorthy
10 months agoGertude
10 months agoKrissy
10 months agoMickie
1 year agoOretha
11 months agoPaola
12 months agoTegan
12 months agoSoledad
12 months agoLina
1 year agoMollie
1 year agoLorriane
11 months agoJerrod
12 months agoKerry
1 year agoPearline
1 year agoLina
1 year ago