Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Herman
3 months agoMatthew
3 months agoShonda
3 months agoVernice
4 months agoNieves
4 months agoBenedict
4 months agoTimothy
4 months agoMoon
4 months agoRobt
5 months agoLucia
5 months agoMary
5 months agoSarina
5 months agoVilma
5 months agoErasmo
5 months agoParis
9 months agoCammy
9 months agoCarman
8 months agoCecily
9 months agoRupert
9 months agoJennifer
9 months agoKristine
10 months agoDorthy
8 months agoGertude
8 months agoKrissy
9 months agoMickie
10 months agoOretha
9 months agoPaola
10 months agoTegan
10 months agoSoledad
10 months agoLina
10 months agoMollie
10 months agoLorriane
10 months agoJerrod
10 months agoKerry
10 months agoPearline
11 months agoLina
11 months ago