Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
36 comments · newest first
HE
Herman 11 months ago
I agree with 3 days, makes sense with the schedule!
MA
Matthew 11 months ago
Wait, how can it be zero days? That seems off.
SH
Shonda 12 months ago
Definitely 4 days, right?
VE
Vernice 12 months ago
I think it should be 1 day delay for Activity H.
NI
Nieves 1 year ago
Activity B is delayed by 3 days now.
BE
Benedict 1 year ago
I feel like the answer is related to the critical path. If Activity B is on it, then it might affect H more than I initially thought.
TI
Timothy 1 year ago
Wait, if Activity B is delayed by three days, does that mean Activity H can only be delayed by one day? I’m not entirely confident about that.
MO
Moon 1 year ago
I think we practiced a similar question where we had to adjust the float based on changes in activity durations. I hope I can apply that here.
RO
Robt 1 year ago
I remember something about total float and how delays in one activity can affect others, but I'm not sure how to calculate it here.
LU
Lucia 1 year ago
Whoa, this is a tricky one. I'm not totally sure how to approach this. Maybe I should sketch out the timeline and dependencies to visualize it better. Gotta be careful with these scheduling questions.
MA
Mary 1 year ago
I've got this! The question is asking how long we can delay Activity H, and since Activity B is delayed by 3 days, we can delay Activity H by the same 3 days. The answer is C, 4 days.
SA
Sarina 1 year ago
Hmm, I'm a bit confused. I need to figure out how the delay in Activity B impacts the timing of Activity H. Let me re-examine the diagram and timeline carefully.
VI
Vilma 1 year ago
Okay, let me think this through step-by-step. If Activity B takes 8 days instead of 5, that means it's delayed by 3 days. Since Activity H depends on Activity B, I can delay Activity H by the same 3 days.
ER
Erasmo 1 year ago
I'm pretty sure Cisco Jabber uses XMPP and UDS for contact searching in an on-premises deployment.
PA
Paris 1 year ago
Well, if Activity B takes 8 days, I guess we'll just have to put Activity H on hold until the cows come home - so that's D) Zero days, right?
CA
Cammy 1 year ago
Wait, does this mean I can take a four-day vacation while we wait for Activity H to start? Sign me up for that delay!
CA
Carman 1 year ago
↳ replying to Cammy
User 4: Sign me up for that delay!
CE
Cecily 1 year ago
↳ replying to Cammy
User 3: Wait, does that mean I can take a four-day vacation while we wait for Activity H to start?
RU
Rupert 1 year ago
↳ replying to Cammy
User 2: We can now delay Activity H by four days.
JE
Jennifer 1 year ago
↳ replying to Cammy
User 1: If Activity B takes eight days instead of five, how long can we delay Activity H?
KR
Kristine 2 years ago
This question is making my head spin! I'm going to go with the answer that sounds the most reasonable - C) Four days. Fingers crossed that's the right choice!
DO
Dorthy 1 year ago
↳ replying to Kristine
User 3: Let's hope we're right, fingers crossed!
GE
Gertude 1 year ago
↳ replying to Kristine
User 2: I agree, it seems like the most reasonable choice.
KR
Krissy 1 year ago
↳ replying to Kristine
User 1: I think the answer is C) Four days.
MI
Mickie 2 years ago
Oh no, my project management skills are being tested! Let me see... If Activity B is delayed, that pushes out Activity H. I'll go with C) Four days, but I'm crossing my fingers!
OR
Oretha 1 year ago
↳ replying to Mickie
Let's hope it's not too big of a delay!
PA
Paola 2 years ago
↳ replying to Mickie
I believe it's D) Zero days.
TE
Tegan 2 years ago
↳ replying to Mickie
I'm not sure, maybe it's A) Three days?
SO
Soledad 2 years ago
↳ replying to Mickie
I think it's C) Four days too.
LI
Lina 2 years ago
That makes sense, thanks for explaining!
MO
Mollie 2 years ago
This is a tricky one! If Activity B is delayed by 3 days, that means the entire critical path is delayed by 3 days. So, the answer has to be C) Four days.
LO
Lorriane 2 years ago
↳ replying to Mollie
Yes, that makes sense. So the answer is C) Four days.
JE
Jerrod 2 years ago
↳ replying to Mollie
I think you're right, if Activity B is delayed by 3 days, then Activity H can be delayed by 4 days.
KE
Kerry 2 years ago
Hmm, let me think about this. If Activity B takes 8 days instead of 5, that would delay the start of Activity H. The question is asking how long can we delay Activity H, so I'm going to go with C) Four days.
PE
Pearline 2 years ago
I disagree, I believe the answer is C) Four days because Activity H is dependent on Activity B.
LI
Lina 2 years ago
I think the answer is A) Three days.