Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Herman
6 months agoMatthew
6 months agoShonda
7 months agoVernice
7 months agoNieves
7 months agoBenedict
7 months agoTimothy
8 months agoMoon
8 months agoRobt
8 months agoLucia
8 months agoMary
8 months agoSarina
8 months agoVilma
8 months agoErasmo
8 months agoParis
1 year agoCammy
1 year agoCarman
11 months agoCecily
12 months agoRupert
12 months agoJennifer
1 year agoKristine
1 year agoDorthy
12 months agoGertude
12 months agoKrissy
1 year agoMickie
1 year agoOretha
1 year agoPaola
1 year agoTegan
1 year agoSoledad
1 year agoLina
1 year agoMollie
1 year agoLorriane
1 year agoJerrod
1 year agoKerry
1 year agoPearline
1 year agoLina
1 year ago