John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the
following activities will he use to make
the schedule models? .
Each correct answer represents a complete solution. Choose all that apply.
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Nan
20 days agoWerner
22 days agoAlethea
6 days agoSabine
10 days agoMarva
1 months agoRosalyn
5 days agoAlfred
1 months agoJacquelyne
17 days agoLawanda
23 days agoRikki
1 months agoKiley
1 months agoNieves
1 months agoSarah
2 months ago