Question #: 52
Topic #: 9
[All PMI-SP Questions]

Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?

Show Suggested Answer Hide Answer
Suggested Answer: D

Beth, the project manager, is responsible for communication with all stakeholders. According to the

PMBOK, the project manager occupies the

center of the interactions between stakeholders and the project itself.

Answer option B is incorrect. Sarah may help with the communications, but she is not responsible

for the communications.

Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the

information.

Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for

communicating with the project

stakeholders.


Contribute your Thoughts:

0/2000 characters
Brynn
4 months ago
Sarah's just the assistant, so I doubt she’s the main contact.
upvoted 0 times
...
Val
4 months ago
Wait, are we sure Thomas isn't involved more directly?
upvoted 0 times
...
Cherry
4 months ago
I agree, Beth is the one in charge of communication.
upvoted 0 times
...
Tatum
4 months ago
No way, it could be each team leader too!
upvoted 0 times
...
Delbert
4 months ago
I think it's definitely Beth. She's the project manager.
upvoted 0 times
...
Myra
5 months ago
I keep mixing up who is responsible for stakeholder communication. Is it possible that Thomas, as the sponsor, could have a role too?
upvoted 0 times
...
Jeannetta
5 months ago
I feel like Sarah, as the administrative assistant, might handle some communication, but it seems like Beth would ultimately be in charge.
upvoted 0 times
...
Jaime
5 months ago
I'm not entirely sure, but I remember a question about communication roles in projects. I think it might be the team leaders instead?
upvoted 0 times
...
Una
5 months ago
I think the project manager, Beth, should be the one responsible for communication with all stakeholders since she oversees the project.
upvoted 0 times
...
Hobert
5 months ago
I'm a bit confused by this question. I'll need to review my notes on file uploads to be sure I understand it.
upvoted 0 times
...
Shay
5 months ago
Okay, I think I've got a good strategy for this. I'll start by getting the current Pod configuration using `kubectl get pod`, then modify it to add the sidecar container and Volume mount. Shouldn't be too difficult.
upvoted 0 times
...
Rodolfo
5 months ago
I might be mixing this up, but I recall that carbonate cracks tend to show a specific pattern. Was it diagonal or something else?
upvoted 0 times
...

Save Cancel