Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide
activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?
A three-point estimate records the optimistic, most likely, and the pessimistic duration
and then records an average for the predicted duration.
Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is
originated with the Program Evaluation
and Review Technique (PERT). PERT charts the following three estimates:
Most likely (TM): The duration of activity based on realistic factors such as resources assigned,
interruptions, etc.
Optimistic (TO): The activity duration based on the best-case scenario
Pessimistic (TP): The activity duration based on the worst-case scenario
The expected (TE) activity duration is a weighted average of these three estimates:
TE = (TO + 4TM + TP) / 6
Duration estimates based on the above equations (sometimes simple average of the three estimates
is also used) provide more accuracy.
Here it is,
TE = ( 24 + 28*4 + 36) / 6
= 272/6
= 29 (approx)
Answer options B, D, and A are incorrect. These are not the valid answers for this question.
Pamella
10 months agoDeangelo
11 months agoJenelle
11 months agoIrma
11 months agoNieves
11 months agoGalen
11 months agoDierdre
11 months agoGlenn
11 months agoMica
11 months agoBobbye
12 months agoBeata
12 months ago