Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 9 Question 41 Discussion

Posted by Lilli on May 03, 2022 at 09:31 PM

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide

activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?

Suggested Answer: C

A three-point estimate records the optimistic, most likely, and the pessimistic duration

and then records an average for the predicted duration.

Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is

originated with the Program Evaluation

and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned,

interruptions, etc.

Optimistic (TO): The activity duration based on the best-case scenario

Pessimistic (TP): The activity duration based on the worst-case scenario

The expected (TE) activity duration is a weighted average of these three estimates:

TE = (TO + 4TM + TP) / 6

Duration estimates based on the above equations (sometimes simple average of the three estimates

is also used) provide more accuracy.

Here it is,

TE = ( 24 + 28*4 + 36) / 6

= 272/6

= 29 (approx)

Answer options B, D, and A are incorrect. These are not the valid answers for this question.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
11 comments · newest first
PA
Pamella 1 year ago
The optimistic, most likely, and pessimistic estimates are key here.
DE
Deangelo 1 year ago
Totally agree, 24 makes the most sense!
JE
Jenelle 1 year ago
Wait, are we sure about those numbers? Seems off.
IR
Irma 1 year ago
I think it's 24 based on the estimates!
NI
Nieves 1 year ago
The PERT formula is (O + 4M + P) / 6.
GA
Galen 1 year ago
I’m a bit confused about how to interpret the chart. Does the PERT analysis always require all three estimates?
DI
Dierdre 1 year ago
I think we need to calculate the weighted average using optimistic, pessimistic, and most likely estimates.
GL
Glenn 1 year ago
I remember we used the PERT formula in class, but I’m not entirely sure how to apply it here.
MI
Mica 1 year ago
I practiced a similar question last week, and I think the answer was around 24, but I can't recall the exact calculations.
BO
Bobbye 1 year ago
Ah, I remember learning about this in class. The answer is D - writing processes that are fast to start up and gracefully shut down.
BE
Beata 1 year ago
This one seems pretty straightforward. I think the answer is Corrective action since the project team is fixing the incorrectly installed fixtures and implementing a standard process going forward.
0/2000 characters

Save Cancel