New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 9 Question 2 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 2
Topic #: 9
[All PMI-SP Questions]

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Show Suggested Answer Hide Answer
Suggested Answer: D

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. "80" is not the same value as ".80". Answer option B is incorrect. 1.02 is the cost performance index. Answer option C is incorrect. 102 is not a valid calculation for this question.


Contribute your Thoughts:

0/2000 characters
Aja
4 months ago
Are you sure about those numbers? Seems off to me.
upvoted 0 times
...
Jarvis
4 months ago
Totally agree, looks like we're behind schedule.
upvoted 0 times
...
Teddy
4 months ago
Wait, is it really only 60% done? That's rough.
upvoted 0 times
...
Dean
4 months ago
I think it's definitely lower than 1.
upvoted 0 times
...
Willodean
4 months ago
The SPI is calculated as EV/PV.
upvoted 0 times
...
Arleen
5 months ago
I feel like I might be overthinking this. If we're only 60% complete, does that mean the SPI is less than 1? I need to double-check my calculations.
upvoted 0 times
...
Ammie
5 months ago
I think the formula is SPI = EV / PV, but I’m confused about how to find the earned value (EV) and planned value (PV) in this scenario.
upvoted 0 times
...
Dortha
5 months ago
I remember something about calculating the SPI using EV and PV, but I'm not entirely sure how to apply it here.
upvoted 0 times
...
Han
5 months ago
I practiced a similar question where we had to determine the SPI, and I think I got it right by using the budget and completion percentage.
upvoted 0 times
...
Jolene
5 months ago
I'm pretty confident the answer is D. C2C makes the most sense since eBay is enabling transactions between regular consumers, not businesses.
upvoted 0 times
...
Alison
5 months ago
Hmm, this looks like a tricky one. I'll need to think through the requirements carefully to determine the right objects to create.
upvoted 0 times
...
Katie
5 months ago
Okay, let me see. I remember MoV is all about maximizing value, so I'm guessing it wouldn't be useful when the asset is already decommissioned or in the operational phase. I'll go with B or C.
upvoted 0 times
...

Save Cancel