You are the project manager for your organization. You are working with your project team to
develop the project schedule. You would like to automate much of the scheduling by using Microsoft
project. Microsoft project as a scheduling tool is an example of what tool and technique for the
Develop Schedule Process?
According to the PMBOK, automated scheduling tools expedite the scheduling process.
The scheduling tool is used in combination with manual methods or further project management
software to carry out the schedule network
analysis to produce an updated project schedule.
Answer option C is incorrect. The project management information system is the complete project
management software package beyond just
the scheduling portion.
Answer option D is incorrect. This is not a valid answer.
Answer option A is incorrect. While the software may be made available as a part of organizational
process assets, the best answer is the
scheduling tool.
Leatha
5 months agoGiuseppe
6 months agoJacquelyne
6 months agoElbert
6 months agoTyra
6 months agoIvette
6 months agoGregoria
7 months agoHermila
7 months agoJarvis
7 months agoJohanna
7 months agoHyun
8 months agoRobt
8 months agoStephen
8 months agoMarquetta
8 months agoBernardo
1 year agoCory
12 months agoTheron
12 months agoTammy
1 year agoTeddy
1 year agoFletcher
1 year agoBrandon
1 year agoCordell
12 months agoDiane
1 year agoEden
1 year agoAdelle
1 year agoLynelle
1 year agoSean
12 months agoCarry
12 months agoBerry
1 year agoJosephine
1 year agoBettina
1 year agoGaynell
1 year agoKayleigh
1 year agoGolda
1 year agoJeannine
1 year agoAhmed
1 year agoRolland
1 year agoJame
1 year agoElmira
1 year agoTimothy
1 year agoBlondell
1 year agoJeniffer
1 year agoSabina
1 year agoMeghann
1 year agoBernardo
1 year agoGiovanna
1 year agoMyrtie
1 year ago