New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 8 Question 54 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 54
Topic #: 8
[All PMI-SP Questions]

Which of the following provides a method to track project progress during project execution against what was planned?

Show Suggested Answer Hide Answer
Suggested Answer: C

A schedule baseline provides a method to track project progress during project

execution against what was planned.

What is schedule baseline?

Schedule baseline is a project schedule used in measuring project progress. It helps provide a

comparison with the actual

progress of work against the schedule and to determine if performance to date is within acceptable

parameters. Any

change caused by change in scope of the project invalidates the original schedule and requires a new

baseline schedule.

Answer options D, A, and B are incorrect. A detailed project budget, team members profile, and

benefit-cost ratio will not help you track

project progress.

What is BCR?

A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that

attempts to summarize

the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or

proposal, expressed in

monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should

be expressed in

discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar

expended.


Contribute your Thoughts:

0/2000 characters
Nada
4 months ago
Benefit-cost ratio doesn’t track progress, just evaluates value.
upvoted 0 times
...
Izetta
4 months ago
Wait, can a schedule baseline really show all progress?
upvoted 0 times
...
Kaycee
4 months ago
Totally agree, schedule baseline is the way to go!
upvoted 0 times
...
Gussie
4 months ago
I think detailed project budget is more important.
upvoted 0 times
...
Lucia
4 months ago
Schedule baseline is key for tracking progress!
upvoted 0 times
...
Anissa
5 months ago
I’m leaning towards the schedule baseline too, but I wonder if team member profiles could play a role in tracking progress as well.
upvoted 0 times
...
Selma
5 months ago
The detailed project budget seems relevant, but I feel like it’s more about costs than actual progress tracking.
upvoted 0 times
...
Sarah
5 months ago
I remember practicing a question about project tracking, and I think the benefit-cost ratio was more about evaluating project viability rather than tracking.
upvoted 0 times
...
Alease
5 months ago
I think the schedule baseline is what we use to track progress, but I'm not entirely sure if it's the only method.
upvoted 0 times
...
Ellsworth
5 months ago
I'm pretty confident I know the differences between XQuery 1.0 and SQL2003 when it comes to handling XML data. I think I can eliminate a couple of these options quickly.
upvoted 0 times
...
Jolene
5 months ago
This question seems pretty straightforward. I think the key is to focus on the concept of generalization and how Mary Lee's compliance has changed over time.
upvoted 0 times
...
Detra
5 months ago
I think the answer might be related to how PE and CE routers connect. MP-eBGP sounds like a possibility, but I need to double-check.
upvoted 0 times
...
Corinne
5 months ago
Hmm, I'm a bit unsure about this one. The 5 C's are important concepts, but I can't quite recall what they all are. I'll have to think this through.
upvoted 0 times
...

Save Cancel