You are the project manager for your organization. You are working through the control schedule
process. According to the PMBOK, there are four inputs to this process. Which one of the following is
NOT an input to the control schedule process?
Schedule data is not an input to the control schedule process. Organizational process
assets are the final input to the control schedule process.
The inputs of schedule control process are as follows:
Project Management Plan
Project Schedule
Work Performance Integration
Organizational Process Assets
Answer option C is incorrect. The project management plan is an input to the control schedule
process.Answer option D is incorrect. The project schedule is an input to the control schedule
process.
Answer option B is incorrect. Work performance information is an input to the control schedule
process.
Haydee
10 months agoJeannetta
11 months agoElbert
11 months agoGeraldo
11 months agoAleisha
11 months agoTandra
11 months agoKathryn
11 months agoJanine
11 months agoEstrella
11 months agoFatima
12 months agoMoon
12 months agoAlecia
12 months agoJeniffer
12 months agoArlene
12 months ago