You are the project manager for your organization. You are working through the control schedule
process. According to the PMBOK, there are four inputs to this process. Which one of the following is
NOT an input to the control schedule process?
Schedule data is not an input to the control schedule process. Organizational process
assets are the final input to the control schedule process.
The inputs of schedule control process are as follows:
Project Management Plan
Project Schedule
Work Performance Integration
Organizational Process Assets
Answer option C is incorrect. The project management plan is an input to the control schedule
process.Answer option D is incorrect. The project schedule is an input to the control schedule
process.
Answer option B is incorrect. Work performance information is an input to the control schedule
process.
Haydee
9 months agoJeannetta
9 months agoElbert
9 months agoGeraldo
9 months agoAleisha
9 months agoTandra
10 months agoKathryn
10 months agoJanine
10 months agoEstrella
10 months agoFatima
10 months agoMoon
10 months agoAlecia
10 months agoJeniffer
10 months agoArlene
10 months ago