PMI-SP Exam - Topic 8 Question 48 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 48
Topic #: 8
[All PMI-SP Questions]

You are the project manager for your organization. You are working through the control schedule

process. According to the PMBOK, there are four inputs to this process. Which one of the following is

NOT an input to the control schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: A

Schedule data is not an input to the control schedule process. Organizational process

assets are the final input to the control schedule process.

The inputs of schedule control process are as follows:

Project Management Plan

Project Schedule

Work Performance Integration

Organizational Process Assets

Answer option C is incorrect. The project management plan is an input to the control schedule

process.Answer option D is incorrect. The project schedule is an input to the control schedule

process.

Answer option B is incorrect. Work performance information is an input to the control schedule

process.


Contribute your Thoughts:

0/2000 characters
Haydee
4 months ago
Work performance information is also an input, just FYI.
upvoted 0 times
...
Jeannetta
4 months ago
Wait, are you sure about that? I thought all of them were inputs!
upvoted 0 times
...
Elbert
4 months ago
Yeah, I agree with Geraldo on that one!
upvoted 0 times
...
Geraldo
4 months ago
I think project schedule is NOT an input.
upvoted 0 times
...
Aleisha
4 months ago
Schedule data is definitely an input.
upvoted 0 times
...
Tandra
5 months ago
I remember the control schedule process involves tracking progress, so I think work performance information is crucial. I just can't recall which one isn't an input!
upvoted 0 times
...
Kathryn
5 months ago
I'm a bit lost here. I feel like all of them could be inputs, but I have a nagging feeling that schedule data might not be one.
upvoted 0 times
...
Janine
5 months ago
I practiced a similar question last week, and I think the project management plan is also an input. So that leaves us with the project schedule or schedule data.
upvoted 0 times
...
Estrella
5 months ago
I think the project schedule is definitely an input, but I'm not sure about the others. I remember something about work performance information being used in monitoring.
upvoted 0 times
...
Fatima
5 months ago
Hmm, I'm a bit confused by the options here. I'm not sure which one would provide the highest mitigation while also staying within the budget. I'll need to think this through carefully.
upvoted 0 times
...
Moon
5 months ago
That sounds similar to the practice question we did about asset rendition management! I think leveraging the Adaptive Image Servlet could be a key part here.
upvoted 0 times
...
Alecia
5 months ago
Okay, I think I've got a handle on this. The key is understanding the implications of the top-down analysis and how that might impact the already-delivered services. I'll need to weigh the options carefully and consider the long-term maintenance and alignment of the service inventory.
upvoted 0 times
...
Jeniffer
5 months ago
Okay, I think I've got a strategy here. TFTP is a simple file transfer protocol, so that part makes sense. Hashing the files afterwards would help verify they weren't tampered with. I'll go with True on this one.
upvoted 0 times
...
Arlene
5 months ago
Option A sounds right to me. Spark is designed for large-scale data processing and analysis, so that's definitely a key use case. I feel good about selecting that answer.
upvoted 0 times
...

Save Cancel