Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 8 Question 121 Discussion

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?
B) $122,845
A) $176,675
C) -$85,000
D) -$51,000

PMI-SP Exam - Topic 8 Question 121 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 121
Topic #: 8
[All PMI-SP Questions]

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

Show Suggested Answer Hide Answer
Suggested Answer: B

There is positive variance of $122,845 on Fred's project. Variances can be either positive or negative.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what was planned for this period in time. The schedule variance is

calculated based on the following formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the

project is right on target.

Answer option C is incorrect. This is the project's variance at completion.

Answer option D is incorrect. This is the cost variance for the project.

Answer option A is incorrect. This is not a valid answer for the project.


Contribute your Thoughts:

0/2000 characters
Nenita
2 days ago
I think the planned value should be based on the BAC and the percentage complete, but I'm a bit confused about how crashing affects the calculations.
upvoted 0 times
...
Noah
7 days ago
I remember we practiced calculating schedule variance, but I'm not sure if I have the formula right. Is it EV minus PV?
upvoted 0 times
...

Save Cancel