Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 8 Question 112 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 112
Topic #: 8
[All PMI-SP Questions]

You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?

Show Suggested Answer Hide Answer
Suggested Answer: D

According to the question, the cost variance of the project is -20, which is a negative

figure. The negative CV depicts that the costs are higher

than planned.

What is CV?

Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are

higher than budgeted

or lower than budgeted. The cost variance is calculated based on the following formula:

CV = Earned Value (EV) - Actual Cost (AC)

A positive value means that spending is less than budgeted, whereas a negative value indicates that

costs are higher than

originally planned for the project.

Answer option B is incorrect. This result is drawn when the CV value is positive.

Answer option A is incorrect. If the CV is zero, it shows that spending is right on target.

Answer option C is incorrect. This result is depicted by viewing the schedule variance (SV), not the

CV.

What is SV?

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead

or behind what was planned for this period in time. The schedule variance is calculated based on the

following formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the

project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.


Contribute your Thoughts:

0/2000 characters
Yup, definitely behind schedule with that CV!
upvoted 0 times
...
Lettie
5 days ago
Wait, are we sure about that? Seems off to me.
upvoted 0 times
...
Ma
10 days ago
Totally agree, that's a clear sign of overspending.
upvoted 0 times
...
Tonette
15 days ago
CV of -20 means costs are higher than planned.
upvoted 0 times
...
Deeann
21 days ago
I believe the CV being -20 definitely suggests that costs exceeded what was budgeted, which points to option D.
upvoted 0 times
...
Merri
26 days ago
I’m a bit confused. Does a negative CV also relate to being behind schedule? I feel like I’ve seen that in other questions.
upvoted 0 times
...
Glory
1 month ago
I remember a practice question where a negative CV indicated overspending. So, I would lean towards option D.
upvoted 0 times
...
Leslee
1 month ago
I think a negative cost variance means that costs are higher than planned, but I'm not completely sure.
upvoted 0 times
...

Save Cancel