Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 8 Question 112 Discussion

Posted by Wade on Mar 05, 2026 at 10:29 PM

You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?

Suggested Answer: D

According to the question, the cost variance of the project is -20, which is a negative

figure. The negative CV depicts that the costs are higher

than planned.

What is CV?

Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are

higher than budgeted

or lower than budgeted. The cost variance is calculated based on the following formula:

CV = Earned Value (EV) - Actual Cost (AC)

A positive value means that spending is less than budgeted, whereas a negative value indicates that

costs are higher than

originally planned for the project.

Answer option B is incorrect. This result is drawn when the CV value is positive.

Answer option A is incorrect. If the CV is zero, it shows that spending is right on target.

Answer option C is incorrect. This result is depicted by viewing the schedule variance (SV), not the

CV.

What is SV?

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead

or behind what was planned for this period in time. The schedule variance is calculated based on the

following formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the

project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
31 comments · newest first
ST
Stephania 1 month ago
Yeah, CV being negative shows we're over budget.
AL
Aleta 1 month ago
Definitely D. We need to control costs better.
MA
Mariann 2 months ago
Agreed, -20 means overspending.
IR
Irene 2 months ago
I think it's D. Costs are higher than planned.
DE
Delmy 2 months ago
It's frustrating, but we need to address this issue.
ED
Edison 2 months ago
Definitely D. We need to control costs better.
BL
Blondell 2 months ago
Yeah, I agree. It shows overspending.
KR
Kris 2 months ago
I think the CV of -20 means costs are higher than planned.
AN
Anastacia 3 months ago
I feel stressed about this. Need to explain to the team.
BE
Beth 3 months ago
Definitely D. We need to control expenses.
BE
Beula 3 months ago
Agreed, -20 means overspending.
LA
Laurena 3 months ago
I think it's D. Costs are higher than planned.
JE
Jerry 3 months ago
Just to clarify, negative CV always indicates a budget issue, right?
MA
Marti 3 months ago
Yup, definitely behind schedule if costs are up.
TO
Tonette 4 months ago
Wait, are we sure about that? I thought it could mean something else.
CO
Corrinne 4 months ago
Totally agree, that's a clear sign of overspending.
AL
Aliza 4 months ago
CV of -20 means costs are higher than planned.
MY
Myrtie 4 months ago
Just to clarify, negative CV is bad news for the budget!
LO
Louvenia 4 months ago
Yep, definitely behind schedule if costs are up like that.
VI
Vincent 6 months ago
Wait, is that really what it means? Sounds off to me.
PA
Pamella 6 months ago
Totally agree, that's a clear sign of overspending.
MA
Mari 6 months ago
CV of -20 means costs are higher than planned.
AN
Anissa 6 months ago
Just to clarify, negative CV = bad news for the budget.
ME
Mee 7 months ago
Yup, definitely behind schedule with that CV!
LE
Lettie 7 months ago
Wait, are we sure about that? Seems off to me.
MA
Ma 7 months ago
Totally agree, that's a clear sign of overspending.
TO
Tonette 7 months ago
CV of -20 means costs are higher than planned.
DE
Deeann 7 months ago
I believe the CV being -20 definitely suggests that costs exceeded what was budgeted, which points to option D.
ME
Merri 7 months ago
I’m a bit confused. Does a negative CV also relate to being behind schedule? I feel like I’ve seen that in other questions.
GL
Glory 8 months ago
I remember a practice question where a negative CV indicated overspending. So, I would lean towards option D.
LE
Leslee 8 months ago
I think a negative cost variance means that costs are higher than planned, but I'm not completely sure.
0/2000 characters

Save Cancel