PMI-SP Exam - Topic 8 Question 111 Discussion

Posted by Daisy on Jan 24, 2026 at 11:54 AM

with an appropriate phrase.

The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

Suggested Answer: A

The procurement SOW consists of a description of some collateral services required, such as performance reporting or post- project operational support for the procured item. The procurement SOW is revised and refined as required when it moves through the procurement process until incorporated into a signed contract award.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
25 comments · newest first
MI
Micheal 4 months ago
I prefer "contract document." It covers everything.
JO
Joesph 4 months ago
"Service level agreement" fits well too.
JO
Jordan 4 months ago
I feel it's "project charter."
DE
Dexter 6 months ago
I think it's "scope statement."
GE
German 6 months ago
Sounds about right, but it can vary by industry.
MI
Ming 6 months ago
I always thought collateral services were optional.
TI
Timmy 6 months ago
Wait, are we sure this is standard practice?
QU
Quiana 7 months ago
Totally agree, it's crucial for clarity.
RO
Ronnie 7 months ago
That's definitely part of the contract!
CA
Casie 7 months ago
The Statement of Work is the way to go here. Covers all the bases, including the collateral services.
LE
Lemuel 7 months ago
Hmm, I'm guessing the answer is "Statement of Work." Gotta love those procurement terms!
DA
Dahlia 7 months ago
I think the missing word is "Statement of Work" - it typically includes details on any additional services required.
AN
Annette 7 months ago
The statement seems to be referring to the scope of the procurement.
DU
Dustin 8 months ago
I’m not confident, but I feel like it could be "project charter" or something similar. I need to double-check my notes!
MA
Mari 8 months ago
This question reminds me of a practice question we did on project documentation. I think it could be "service level agreement," but I could be mixing it up.
ER
Ernie 9 months ago
I remember something about "scope of work" being related to collateral services, but it feels a bit fuzzy.
DE
Deangelo 9 months ago
I think the answer might be "statement of work," but I'm not entirely sure if that's the right term for this context.
DO
Dorathy 9 months ago
Hmm, the "collateral services" part is throwing me off a bit. I'm thinking it might be something like "supplemental services" or "ancillary services" description. But I'm not 100% confident on that. Guess I'll have to think it through carefully.
SH
Shawna 9 months ago
I've got an idea - the phrase they're looking for is probably "statement of work." That's the section that outlines all the requirements and deliverables, including any supplementary services. Seems like a good educated guess to me.
KR
Kristin 9 months ago
I'm a little unsure about this one. The wording is a bit vague, so I'd want to make sure I understand exactly what type of procurement document they're referring to. Maybe I'd start by asking the instructor to clarify the context.
DA
Danica 9 months ago
Okay, let's see. The blank is asking for a phrase that describes the part of the procurement document that covers any additional services needed. I'm thinking it might be something like "scope of work" or "service level agreement."
CL
Clemencia 10 months ago
Hmm, this seems like it's asking about the contents of a procurement document. I'd start by thinking through the key elements that are typically included in those types of documents.
GL
Glendora 3 months ago
↳ replying to Clemencia
Definitely! Performance reporting is key for success.
CO
Colene 4 months ago
↳ replying to Clemencia
Yeah, collateral services are important!
PE
Pearlie 4 months ago
↳ replying to Clemencia
Sounds like it’s about procurement details.
0/2000 characters

Save Cancel