You are the project manager of the NNN Project. Stakeholders in the two-year project have
requested to send status reports to them via email every week. You have agreed and are sending the
reports on each Thursday. After six months of the project, the stakeholders are pleased with the
project progress and they would like you to reduce the status reports to every two weeks. What
process will examine the change to this project process and implement it in the project?
Although this appears to be a simple change the project manager must still follow the
rules of the project's change control system. Perform
Integrated Change Control is the process of reviewing all change requests, approving changes, and
controlling changes to the deliverables
and organizational process assets in a project. Perform Integrated Change Control has to do with
influencing the things that cause change,
determining that the change is required or has happened, and managing the change.
Answer option D is incorrect. Communications management is the execution of the communications
management plan.
Answer option A is incorrect. The project change control process not valid as it's the parent of the
integrated change control process, which is
more accurate for this question.
Answer option C is incorrect. Configuration management is the documentation and control of the
product's features and functions.
Felix
3 days agoTasia
8 days agoArthur
13 days agoBernardo
18 days agoMa
23 days agoCarisa
29 days agoDorothea
1 month agoGraciela
1 month agoAlysa
1 month agoKristin
2 months agoMari
2 months agoElden
2 months ago