Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.
The project's Communications Management Plan defines what information will be distributed, when
it will be distributed, to whom it will be
distributed, and the modality of the information.
Answer option D is incorrect. The Schedule Management Plan defines the project work, when the
project work will happen, resource
utilization, and how the schedule will be monitored and controlled.
Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder
Management Plan.
Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be
created, how the changes will be allowed,
how the scope will be executed, monitored and controlled, and finally closed.
Carmen
13 days agoReed
15 days agoMel
18 days agoRenay
10 days agoDonte
25 days agoLacey
3 days agoCasie
13 days agoTrevor
1 months agoHillary
2 days agoCorinne
9 days agoIlene
1 months agoTiffiny
2 months agoBrandee
2 months ago