Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 77 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 77
Topic #: 7
[All PMI-SP Questions]

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Show Suggested Answer Hide Answer
Suggested Answer: B

The project's Communications Management Plan defines what information will be distributed, when

it will be distributed, to whom it will be

distributed, and the modality of the information.

Answer option D is incorrect. The Schedule Management Plan defines the project work, when the

project work will happen, resource

utilization, and how the schedule will be monitored and controlled.

Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder

Management Plan.

Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be

created, how the changes will be allowed,

how the scope will be executed, monitored and controlled, and finally closed.


Contribute your Thoughts:

Carmen
13 days ago
I'm just happy they didn't ask about the project manager's favorite flavor of ice cream. That would have really thrown me for a loop!
upvoted 0 times
...
Reed
15 days ago
This is a slam dunk - A, B, and C are the way to go. I could do this in my sleep... or while sleepwalking, for that matter.
upvoted 0 times
...
Mel
18 days ago
Wait, I thought the project manager's breakfast order was a key input. Guess I've been studying the wrong material.
upvoted 0 times
Renay
10 days ago
A) Procurement document
upvoted 0 times
...
...
Donte
25 days ago
I'm pretty sure the business case is the most important input here. Can't have a project without a solid business justification!
upvoted 0 times
Lacey
3 days ago
B) Contract
upvoted 0 times
...
Casie
13 days ago
A) Procurement document
upvoted 0 times
...
...
Trevor
1 months ago
A, B, and C are definitely the inputs to the Develop Project Charter process. D is a bit of a stretch, though.
upvoted 0 times
Hillary
2 days ago
I agree, D does seem like a bit of a stretch.
upvoted 0 times
...
Corinne
9 days ago
A, B, and C are definitely the inputs to the Develop Project Charter process.
upvoted 0 times
...
...
Ilene
1 months ago
I believe A) Procurement document and B) Contract are also inputs because they provide important information for the project charter.
upvoted 0 times
...
Tiffiny
2 months ago
I agree with Brandee. Those two inputs make sense for developing the project charter.
upvoted 0 times
...
Brandee
2 months ago
I think the inputs are C) Business case and D) Project statement of work.
upvoted 0 times
...

Save Cancel