PMI-SP Exam - Topic 7 Question 51 Discussion

Posted by Junita on May 04, 2022 at 11:34 PM

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts

related to the outputs of the control

schedule process. Which of the following is an output of the control schedule process?

Suggested Answer: C

Only change request is a valid answer. The five outputs of the control schedule process

are work performance measurements, organizational

process assets updates, change requests, the project management plan updates, and project

document updates.

Change requests are requests to expand or reduce the project scope, modify policies, processes,

plans, or procedures, modify costs or

budgets or revise schedules. These requests for a change can be direct or indirect, externally or

internally initiated, and legally or contractually

imposed or optional. A Project Manager needs to ensure that only formally documented requested

changes are processed and only approved

change requests are implemented.

Answer option D is incorrect. Activity resource requirement is not an output of the control schedule

process.

Answer option A is incorrect. The project schedule is not an output of the control schedule process.

Answer option B is incorrect. Lessons learned is not an output of the control schedule process.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
11 comments · newest first
PA
Patria 1 year ago
Lessons learned are usually from the closing process, not control.
CH
Cheryl 1 year ago
Yeah, project schedule makes the most sense!
KI
Kiera 1 year ago
Wait, are we sure about that?
CH
Chaya 1 year ago
I think it's change requests, right?
BA
Barbra 1 year ago
The output is definitely the project schedule!
SO
Sommer 1 year ago
Activity resource requirements? That sounds like it’s more about planning too. I’m confused about what exactly comes out of control scheduling.
VA
Vanna 1 year ago
Lessons learned seem more like a final output, not something from the control schedule process. I’m leaning towards change requests.
BE
Ben 1 year ago
I remember practicing a question like this, and I think the project schedule is more about planning than controlling.
GE
Gerald 1 year ago
I think the control schedule process outputs something related to changes, but I'm not entirely sure if it's a change request or something else.
CA
Carman 1 year ago
Hmm, I'm a little unsure about the difference between the options here. I'll need to think through how data is processed in a PDI transformation to figure out the right answers.
JU
Junita 1 year ago
Okay, let me see. An intranet is a private network within an organization, while an extranet allows external access. Ethernet is a local area network technology, and the Internet is the global public network. I think C - Intranet is the best answer here.
0/2000 characters

Save Cancel