Harry works as a project manager for BlueWell Inc. He is determining the budget of the project.
According to the PMBOK, there are seven
inputs to this process. Which one of the following is NOT an input to the determine budget process?
Reserve analysis is not an input to the determine budget process. It is a technique used
for determining the budget.
The inputs to the determine budget process are as follows:
Activity cost estimates
Basis of estimates
Scope baseline
Project schedule
Resource calendars
Contracts
Organizational process assets