Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 7 Question 115 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 115
Topic #: 7
[All PMI-SP Questions]

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

Based on this figure, what is the critical path of this project?

Show Suggested Answer Hide Answer
Suggested Answer: D

The activity nodes of path ACFGJ equals 26 days and is the longest path to completion - it is the

critical path.

ACFGJ= A(4)+C(8)+F(4)+G(6)+J(4)=26

What is a critical path?

A critical path is the sequence of project activities, which add up to the longest overall duration. This

determines the

shortest time possible to complete the project. Any delay of an activity on the critical path directly

impacts the planned

project completion date (i.e. there is no float on the critical path). A project can have several,

parallel, near critical paths. An

additional parallel path through the network with the total durations shorter than the critical path is

called a sub-critical or

non-critical path.

These results allow managers to prioritize activities for the effective management of project

completion, and to shorten the

planned critical path of a project by pruning critical path activities, by 'fast tracking' (i.e., performing

more activities in

parallel), and/or by 'crashing the critical path' (i.e., shortening the durations of critical path activities

by adding resources).

Answer option A is incorrect. ABEHJ takes only 22 days to complete; it is not the critical path.

ABEHJ=A(4)+B(5)+E(2)+H(7)+J(4)=22

Answer option C is incorrect. ADGJ takes only 15 days to complete; it is not the critical path.

ADGJ=A(4)+D(1)+G(6)+J(4)=15

Answer option B is incorrect. ACFIJ takes only 23 days to complete; it is not the critical path.

ACFIJ=A(4)+C(8)+F(4)+I(3)+J(4)=23


Contribute your Thoughts:

0/2000 characters
Janey
2 days ago
I practiced a similar question last week, and I believe the critical path is ACFGJ. It seems to have the most activities.
upvoted 0 times
...
Danica
7 days ago
I think the critical path is ABEHJ, but I'm not entirely sure. I remember something about the longest path being the critical one.
upvoted 0 times
...

Save Cancel