Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 7 Question 115 Discussion

Posted by Solange on May 06, 2026 at 03:43 PM

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

Based on this figure, what is the critical path of this project?

Suggested Answer: D

The activity nodes of path ACFGJ equals 26 days and is the longest path to completion - it is the

critical path.

ACFGJ= A(4)+C(8)+F(4)+G(6)+J(4)=26

What is a critical path?

A critical path is the sequence of project activities, which add up to the longest overall duration. This

determines the

shortest time possible to complete the project. Any delay of an activity on the critical path directly

impacts the planned

project completion date (i.e. there is no float on the critical path). A project can have several,

parallel, near critical paths. An

additional parallel path through the network with the total durations shorter than the critical path is

called a sub-critical or

non-critical path.

These results allow managers to prioritize activities for the effective management of project

completion, and to shorten the

planned critical path of a project by pruning critical path activities, by 'fast tracking' (i.e., performing

more activities in

parallel), and/or by 'crashing the critical path' (i.e., shortening the durations of critical path activities

by adding resources).

Answer option A is incorrect. ABEHJ takes only 22 days to complete; it is not the critical path.

ABEHJ=A(4)+B(5)+E(2)+H(7)+J(4)=22

Answer option C is incorrect. ADGJ takes only 15 days to complete; it is not the critical path.

ADGJ=A(4)+D(1)+G(6)+J(4)=15

Answer option B is incorrect. ACFIJ takes only 23 days to complete; it is not the critical path.

ACFIJ=A(4)+C(8)+F(4)+I(3)+J(4)=23


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
28 comments · newest first
DA
Daren 6 days ago
Let's see what the exam says!
AN
An 11 days ago
Yes, that's why I think ABEHJ is best.
MA
Marleen 17 days ago
Critical path needs to be the longest, right?
MI
Mirta 22 days ago
ACFGJ has a good flow, but not the longest.
LO
Louisa 27 days ago
ACFGJ could be a contender as well.
DA
Daren 1 month ago
ADGJ? Not sure about that one.
AN
An 1 month ago
I feel like ADGJ might be overlooked.
MA
Marleen 1 month ago
But ACFIJ has fewer dependencies.
LO
Louisa 2 months ago
ACFIJ has some strong connections too.
MI
Mirta 2 months ago
I agree with Daren, ABEHJ looks solid.
DA
Daren 2 months ago
ABEHJ seems to have the longest duration.
MA
Marleen 2 months ago
Really? I lean towards ACFIJ.
DA
Daren 2 months ago
I think it's ABEHJ.
AN
Antonio 2 months ago
I believe ACFGJ is the answer. It maximizes efficiency.
BL
Blondell 3 months ago
ABEHJ seems right. It connects key activities directly.
LO
Loreta 3 months ago
ACFIJ makes sense to me. It flows well through the diagram.
JO
Joaquin 3 months ago
I’m leaning towards ACFGJ. It covers more tasks.
NI
Nicolette 3 months ago
I feel ACFIJ might be it. It has more dependencies.
LA
Laticia 3 months ago
I think the critical path is ABEHJ. It looks the longest.
LI
Lindy 3 months ago
Totally agree with ABEHJ being the critical path!
SE
Selma 4 months ago
Wait, are we sure about ABEHJ? Seems off.
MU
Muriel 4 months ago
Definitely ABEHJ, no doubt!
CH
Charlesetta 4 months ago
I think it's ACFGJ, though.
JA
Jarod 4 months ago
The critical path is ABEHJ.
LA
Lavonna 4 months ago
I recall that the critical path is crucial for project scheduling, but I can't remember if it's ACFIJ or ACFGJ. I need to look at the dependencies again.
MI
Ming 6 months ago
I'm a bit confused about how to determine the critical path from the diagram. I thought it was ADGJ, but I need to double-check my calculations.
JA
Janey 6 months ago
I practiced a similar question last week, and I believe the critical path is ACFGJ. It seems to have the most activities.
DA
Danica 6 months ago
I think the critical path is ABEHJ, but I'm not entirely sure. I remember something about the longest path being the critical one.
0/2000 characters

Save Cancel