Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?
The estimate at completion (EAC) formula is the Budget at Completion (BAC)/Cost
Performance Index (CPI). In this instance, the CPI is .78 and
the BAC is $344,000. Cathy's project isn't doing too well.
Answer option D is incorrect. This value represents the estimate to complete for the project.
Answer option B is incorrect. This value represents the negative cost variance.
Answer option A is incorrect. This value represents the negative value the project will have once all
the work is completed.
Timothy
10 months agoFreeman
11 months agoIdella
11 months agoTenesha
11 months agoDesirae
11 months agoTamra
11 months agoGlory
11 months agoNadine
11 months agoKerrie
11 months agoStephen
12 months agoReena
12 months agoMariko
12 months agoStephane
12 months agoGenevive
12 months agoHelga
12 months ago