Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 7 Question 103 Discussion

Della works as a Project Manager for Blue Well Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?
A) Project is right on target.
B) Project is ahead of the schedule.
C) Project is behind the schedule.
D) Costs are higher than planned.

PMI-SP Exam - Topic 7 Question 103 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 103
Topic #: 7
[All PMI-SP Questions]

Della works as a Project Manager for Blue Well Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?

Show Suggested Answer Hide Answer
Suggested Answer: A

According to the question, the schedule variance (SV) of the project is zero. A value of 0

indicates that the project is right on target.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option C is incorrect. The negative SV means that project is behind the schedule.

Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the

project.

Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned

schedule.


Contribute your Thoughts:

0/2000 characters
Theola
5 months ago
I thought zero SV could mean something else too...
upvoted 0 times
...
Twana
6 months ago
Totally agree, that's a good sign!
upvoted 0 times
...
Eura
6 months ago
SV of zero means we're right on target!
upvoted 0 times
...
In
6 months ago
Wait, does that really mean we're not behind?
upvoted 0 times
...
Lavonda
6 months ago
Fingers crossed it stays that way!
upvoted 0 times
...
Michel
7 months ago
I believe zero SV means the project is neither ahead nor behind, so it should be option A, right?
upvoted 0 times
...
Annita
7 months ago
I’m a bit confused; does a zero SV mean we’re ahead or just on schedule? I feel like I need to double-check my notes.
upvoted 0 times
...
Xenia
7 months ago
I remember practicing a question like this where a zero SV indicated that the project is right on target. I hope that’s still correct!
upvoted 0 times
...
Martina
7 months ago
I think a zero schedule variance means the project is on track, but I'm not entirely sure if that’s the only implication.
upvoted 0 times
...
Aja
7 months ago
Hmm, I'm not sure about this one. I'll need to review my notes on earned value management to make sure I understand schedule variance and what a zero value means.
upvoted 0 times
...
Roy
8 months ago
I'm pretty confident the answer is A. A schedule variance of zero indicates the project is progressing as planned, neither ahead nor behind schedule.
upvoted 0 times
...
Kerry
8 months ago
Okay, I've got this. A schedule variance of zero means the project is exactly on schedule, not ahead or behind. That's option A - the project is right on target.
upvoted 0 times
...
Raylene
8 months ago
I'm a bit confused here. If the schedule variance is zero, does that mean the project is ahead or behind schedule? I'll need to think this through carefully.
upvoted 0 times
...
Carmelina
8 months ago
Hmm, a schedule variance of zero? That seems straightforward, the project must be right on target.
upvoted 0 times
...
Niesha
10 months ago
Option A all the way. Who needs a schedule when you've got perfect timing, am I right?
upvoted 0 times
Chara
8 months ago
That's great news, keep up the good work!
upvoted 0 times
...
Shawna
9 months ago
Exactly, we're right on track with our project.
upvoted 0 times
...
Delsie
10 months ago
SV of zero means the project is right on target.
upvoted 0 times
...
...
Keshia
10 months ago
That's a good point, Helaine. We should always consider other performance indicators as well.
upvoted 0 times
...
Helaine
10 months ago
But what if the project is actually behind schedule and just happened to balance out with other factors?
upvoted 0 times
...
Yuonne
11 months ago
Wait, a zero SV? That's like hitting the bullseye on the first try. I'm impressed!
upvoted 0 times
Elza
10 months ago
B) Project is ahead of the schedule.
upvoted 0 times
...
Yuonne
10 months ago
A) Project is right on target.
upvoted 0 times
...
...
Keva
11 months ago
Hah, easy one! A zero SV means the project is exactly as planned, no delays or early finishes.
upvoted 0 times
Lorean
10 months ago
Hah, easy one! A zero SV means the project is exactly as planned, no delays or early finishes.
upvoted 0 times
...
Evette
10 months ago
A) Project is right on target.
upvoted 0 times
...
...
Leigha
11 months ago
I agree with Cherri, zero schedule variance means we are on track.
upvoted 0 times
...
Lyndia
11 months ago
A zero schedule variance means the project is right on target. Nailed it!
upvoted 0 times
Deeanna
10 months ago
Team Leader: Thank you, we're on track!
upvoted 0 times
...
Galen
10 months ago
Della: That means the project is right on target. Great job!
upvoted 0 times
...
Ceola
11 months ago
Team Leader: The schedule variance of our project is zero.
upvoted 0 times
...
...
Cherri
11 months ago
I think the answer is A) Project is right on target.
upvoted 0 times
...

Save Cancel