Della works as a Project Manager for Blue Well Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?
According to the question, the schedule variance (SV) of the project is zero. A value of 0
indicates that the project is right on target.
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that
the schedule is ahead or behind what
was planned for this period in time. The schedule variance is calculated based on the following
formula:
SV = Earned Value (EV) - Planned Value (PV)
If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater
than 0 shows that the project is ahead of
the planned schedule. A value of 0 indicates that the project is right on target.
Answer option C is incorrect. The negative SV means that project is behind the schedule.
Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the
project.
Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned
schedule.
Theola
9 months agoTwana
9 months agoEura
9 months agoIn
9 months agoLavonda
10 months agoMichel
10 months agoAnnita
10 months agoXenia
10 months agoMartina
11 months agoAja
11 months agoRoy
11 months agoKerry
11 months agoRaylene
11 months agoCarmelina
11 months agoNiesha
1 year agoChara
12 months agoShawna
12 months agoDelsie
1 year agoKeshia
1 year agoHelaine
1 year agoYuonne
1 year agoElza
1 year agoYuonne
1 year agoKeva
1 year agoLorean
1 year agoEvette
1 year agoLeigha
1 year agoLyndia
1 year agoDeeanna
1 year agoGalen
1 year agoCeola
1 year agoCherri
1 year ago