Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Melvin
3 months agoTasia
3 months agoRodolfo
3 months agoLeota
4 months agoDevora
4 months agoFernanda
4 months agoTori
4 months agoDevorah
4 months agoNadine
5 months agoVicente
5 months agoMyra
5 months agoReta
5 months agoEdmond
5 months agoBeula
9 months agoMichael
9 months agoWilda
9 months agoFlo
8 months agoDarrin
8 months agoGlenn
8 months agoCarrol
9 months agoTegan
9 months agoLeota
8 months agoMickie
8 months agoFernanda
8 months agoEleonore
10 months agoPa
8 months agoJules
8 months agoJina
9 months agoDesmond
11 months agoLaquita
11 months agoKasandra
11 months ago