Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 97 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 97
Topic #: 6
[All PMI-SP Questions]

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Beula
3 hours ago
You know, this reminds me of that time I accidentally spilled paint on my cat. Good times, good times.
upvoted 0 times
...
Michael
1 days ago
I don't know, guys. All this talk about painting and carpets is making me hungry. Anyone up for a paint-themed snack break?
upvoted 0 times
...
Wilda
5 days ago
Okay, let's see. A and D just seem like Band-Aids, but C? That's thinking outside the box. I bet Joe's going to get a raise for this one.
upvoted 0 times
...
Tegan
7 days ago
Hmm, I was leaning towards B, but now I'm not so sure. Maybe C is the way to go. It's like a magical time-keeper activity!
upvoted 0 times
...
Eleonore
25 days ago
Option C looks like the perfect solution. A dummy activity to account for the drying time? Genius!
upvoted 0 times
...
Desmond
1 months ago
I think creating a dummy activity for the drying process is the most effective solution.
upvoted 0 times
...
Laquita
2 months ago
I disagree, I believe changing the relationship to finish-to-finish is the way to go.
upvoted 0 times
...
Kasandra
2 months ago
I think the best approach is to add lead time to the painting activity.
upvoted 0 times
...

Save Cancel