PMI-SP Exam - Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Paris
3 months ago
The correct answer is C, project schedule network diagrams.
upvoted 0 times
...
Margart
3 months ago
I disagree, the activity list should be a must-have.
upvoted 0 times
...
Dana
3 months ago
Wait, are project schedule network diagrams really not needed?
upvoted 0 times
...
Tresa
4 months ago
I think the milestone list is essential too!
upvoted 0 times
...
Sophia
4 months ago
The project scope statement is definitely needed for sequencing.
upvoted 0 times
...
Martin
4 months ago
I have a vague memory that the project scope statement might not be directly used in the sequencing process, but I could be wrong.
upvoted 0 times
...
Emily
4 months ago
I practiced a similar question, and I feel like the activity list is essential for sequencing, so it can't be the answer.
upvoted 0 times
...
William
4 months ago
I think the milestone list is definitely needed for sequencing, but I can't recall if the project schedule network diagrams are part of it.
upvoted 0 times
...
Jutta
5 months ago
I remember that the project scope statement is important, but I'm not sure if it's one of the inputs for sequencing.
upvoted 0 times
...
Willis
5 months ago
Wait, is the activity list really not one of the required documents? I thought that was a key input. Let me double-check the PMBOK guide to make sure I have this right.
upvoted 0 times
...
Jennie
5 months ago
Okay, I've got this. The four documents we need for activity sequencing are the project scope statement, milestone list, project schedule network diagrams, and activity list. I'm pretty sure the activity list is not one of those four, so I'll go with that as the answer.
upvoted 0 times
...
Margurite
5 months ago
Hmm, I'm a little unsure about this one. I know we need organizational process assets, but I can't quite remember all the other required documents. Let me think this through step-by-step.
upvoted 0 times
...
Vashti
5 months ago
This seems like a straightforward question about project management inputs. I'm pretty confident I know the answer, but I'll double-check the process assets and documents needed for activity sequencing just to be sure.
upvoted 0 times
...
Rolland
5 months ago
Okay, let's see here. The question is asking what we should do first, so I'm guessing the answer is going to be a setup or configuration step, rather than a cmdlet to run. I'm leaning towards option B, creating an Exact Data Match (EDM) schema, since that seems like it could be a prerequisite for the regulatory record functionality.
upvoted 0 times
...
Merilyn
5 months ago
I've got a good understanding of system scope and context scope, so I think I can handle this question. I'll just need to focus on identifying the grey zones mentioned in the prompt.
upvoted 0 times
...
Nakisha
5 months ago
Okay, I think I've got a strategy here. I'll focus on the two options that involve using Cloud Discovery to redeploy the Defenders, since that seems like the safest approach.
upvoted 0 times
...
Mila
5 months ago
This question seems straightforward. I think the key is to focus on the service-orientation principle that would help hide the underlying implementation details from the client.
upvoted 0 times
...
Kristian
10 months ago
Ah, the project scope statement. The one document that's thicker than the entire project plan. No wonder they don't want us to use that one.
upvoted 0 times
...
Viva
10 months ago
Wait, we need to sequence the activities? I thought we were just going to throw them all in a hat and draw them out randomly. Where's the fun in that?
upvoted 0 times
Eulah
8 months ago
D) Activity list
upvoted 0 times
...
Helaine
9 months ago
C) Project schedule network diagrams
upvoted 0 times
...
Margart
9 months ago
B) Milestone list
upvoted 0 times
...
Tamesha
9 months ago
A) Project scope statement
upvoted 0 times
...
...
Chauncey
10 months ago
Project schedule network diagrams? That's a new one. I guess the project manager is really going for the advanced level here.
upvoted 0 times
Desire
9 months ago
C) Project schedule network diagrams
upvoted 0 times
...
Moon
9 months ago
B) Milestone list
upvoted 0 times
...
Abraham
9 months ago
A) Project scope statement
upvoted 0 times
...
...
Glory
10 months ago
Ah, the activity list is a no-brainer. How can you sequence activities without the actual list of activities? It's like trying to bake a cake without ingredients.
upvoted 0 times
Ashley
9 months ago
User 3: Agreed, it's like trying to bake a cake without ingredients.
upvoted 0 times
...
Anissa
9 months ago
User 2: Yeah, that makes sense. You can't sequence activities without the actual list of activities.
upvoted 0 times
...
Marylou
9 months ago
User 1: I think the answer is D) Activity list.
upvoted 0 times
...
...
Jettie
10 months ago
The milestone list sounds like it would be really helpful for this process. I can't imagine trying to sequence activities without that.
upvoted 0 times
Shakira
8 months ago
D) Activity list
upvoted 0 times
...
Gabriele
9 months ago
C) Project schedule network diagrams
upvoted 0 times
...
Domitila
10 months ago
B) Milestone list
upvoted 0 times
...
Mitzie
10 months ago
A) Project scope statement
upvoted 0 times
...
...
Henriette
11 months ago
Hmm, I see your point. But I still think it's B) Milestone list because we need that for tracking project progress.
upvoted 0 times
...
Mickie
11 months ago
Hmm, the project scope statement is definitely one of the key inputs for activity sequencing. I'm pretty sure that's a must-have document.
upvoted 0 times
Leana
9 months ago
D) Activity list
upvoted 0 times
...
Wilda
9 months ago
C) Project schedule network diagrams
upvoted 0 times
...
Alica
10 months ago
B) Milestone list
upvoted 0 times
...
Teddy
10 months ago
A) Project scope statement
upvoted 0 times
...
...
Gracia
11 months ago
I disagree, I believe the answer is C) Project schedule network diagrams.
upvoted 0 times
...
Henriette
11 months ago
I think the answer is B) Milestone list.
upvoted 0 times
...

Save Cancel