PMI-SP Exam - Topic 6 Question 80 Discussion

Posted by Andree on Jun 18, 2024 at 11:04 PM

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Suggested Answer: A

Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
44 comments · newest first
PA
Paris 11 months ago
The correct answer is C, project schedule network diagrams.
MA
Margart 11 months ago
I disagree, the activity list should be a must-have.
DA
Dana 12 months ago
Wait, are project schedule network diagrams really not needed?
TR
Tresa 12 months ago
I think the milestone list is essential too!
SO
Sophia 1 year ago
The project scope statement is definitely needed for sequencing.
MA
Martin 1 year ago
I have a vague memory that the project scope statement might not be directly used in the sequencing process, but I could be wrong.
EM
Emily 1 year ago
I practiced a similar question, and I feel like the activity list is essential for sequencing, so it can't be the answer.
WI
William 1 year ago
I think the milestone list is definitely needed for sequencing, but I can't recall if the project schedule network diagrams are part of it.
JU
Jutta 1 year ago
I remember that the project scope statement is important, but I'm not sure if it's one of the inputs for sequencing.
WI
Willis 1 year ago
Wait, is the activity list really not one of the required documents? I thought that was a key input. Let me double-check the PMBOK guide to make sure I have this right.
JE
Jennie 1 year ago
Okay, I've got this. The four documents we need for activity sequencing are the project scope statement, milestone list, project schedule network diagrams, and activity list. I'm pretty sure the activity list is not one of those four, so I'll go with that as the answer.
MA
Margurite 1 year ago
Hmm, I'm a little unsure about this one. I know we need organizational process assets, but I can't quite remember all the other required documents. Let me think this through step-by-step.
VA
Vashti 1 year ago
This seems like a straightforward question about project management inputs. I'm pretty confident I know the answer, but I'll double-check the process assets and documents needed for activity sequencing just to be sure.
RO
Rolland 1 year ago
Okay, let's see here. The question is asking what we should do first, so I'm guessing the answer is going to be a setup or configuration step, rather than a cmdlet to run. I'm leaning towards option B, creating an Exact Data Match (EDM) schema, since that seems like it could be a prerequisite for the regulatory record functionality.
ME
Merilyn 1 year ago
I've got a good understanding of system scope and context scope, so I think I can handle this question. I'll just need to focus on identifying the grey zones mentioned in the prompt.
NA
Nakisha 1 year ago
Okay, I think I've got a strategy here. I'll focus on the two options that involve using Cloud Discovery to redeploy the Defenders, since that seems like the safest approach.
MI
Mila 1 year ago
This question seems straightforward. I think the key is to focus on the service-orientation principle that would help hide the underlying implementation details from the client.
KR
Kristian 1 year ago
Ah, the project scope statement. The one document that's thicker than the entire project plan. No wonder they don't want us to use that one.
VI
Viva 1 year ago
Wait, we need to sequence the activities? I thought we were just going to throw them all in a hat and draw them out randomly. Where's the fun in that?
EU
Eulah 1 year ago
↳ replying to Viva
D) Activity list
HE
Helaine 1 year ago
↳ replying to Viva
C) Project schedule network diagrams
MA
Margart 1 year ago
↳ replying to Viva
B) Milestone list
TA
Tamesha 1 year ago
↳ replying to Viva
A) Project scope statement
CH
Chauncey 2 years ago
Project schedule network diagrams? That's a new one. I guess the project manager is really going for the advanced level here.
DE
Desire 1 year ago
↳ replying to Chauncey
C) Project schedule network diagrams
MO
Moon 1 year ago
↳ replying to Chauncey
B) Milestone list
AB
Abraham 1 year ago
↳ replying to Chauncey
A) Project scope statement
GL
Glory 2 years ago
Ah, the activity list is a no-brainer. How can you sequence activities without the actual list of activities? It's like trying to bake a cake without ingredients.
AS
Ashley 1 year ago
↳ replying to Glory
User 3: Agreed, it's like trying to bake a cake without ingredients.
AN
Anissa 1 year ago
↳ replying to Glory
User 2: Yeah, that makes sense. You can't sequence activities without the actual list of activities.
MA
Marylou 1 year ago
↳ replying to Glory
User 1: I think the answer is D) Activity list.
JE
Jettie 2 years ago
The milestone list sounds like it would be really helpful for this process. I can't imagine trying to sequence activities without that.
SH
Shakira 1 year ago
↳ replying to Jettie
D) Activity list
GA
Gabriele 1 year ago
↳ replying to Jettie
C) Project schedule network diagrams
DO
Domitila 1 year ago
↳ replying to Jettie
B) Milestone list
MI
Mitzie 2 years ago
↳ replying to Jettie
A) Project scope statement
HE
Henriette 2 years ago
Hmm, I see your point. But I still think it's B) Milestone list because we need that for tracking project progress.
MI
Mickie 2 years ago
Hmm, the project scope statement is definitely one of the key inputs for activity sequencing. I'm pretty sure that's a must-have document.
LE
Leana 1 year ago
↳ replying to Mickie
D) Activity list
WI
Wilda 1 year ago
↳ replying to Mickie
C) Project schedule network diagrams
AL
Alica 2 years ago
↳ replying to Mickie
B) Milestone list
TE
Teddy 2 years ago
↳ replying to Mickie
A) Project scope statement
GR
Gracia 2 years ago
I disagree, I believe the answer is C) Project schedule network diagrams.
HE
Henriette 2 years ago
I think the answer is B) Milestone list.