Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kristian
11 days ago
Ah, the project scope statement. The one document that's thicker than the entire project plan. No wonder they don't want us to use that one.
upvoted 0 times
...
Viva
13 days ago
Wait, we need to sequence the activities? I thought we were just going to throw them all in a hat and draw them out randomly. Where's the fun in that?
upvoted 0 times
...
Chauncey
18 days ago
Project schedule network diagrams? That's a new one. I guess the project manager is really going for the advanced level here.
upvoted 0 times
Abraham
8 days ago
A) Project scope statement
upvoted 0 times
...
...
Glory
21 days ago
Ah, the activity list is a no-brainer. How can you sequence activities without the actual list of activities? It's like trying to bake a cake without ingredients.
upvoted 0 times
...
Jettie
28 days ago
The milestone list sounds like it would be really helpful for this process. I can't imagine trying to sequence activities without that.
upvoted 0 times
Domitila
13 days ago
B) Milestone list
upvoted 0 times
...
Mitzie
21 days ago
A) Project scope statement
upvoted 0 times
...
...
Henriette
1 months ago
Hmm, I see your point. But I still think it's B) Milestone list because we need that for tracking project progress.
upvoted 0 times
...
Mickie
2 months ago
Hmm, the project scope statement is definitely one of the key inputs for activity sequencing. I'm pretty sure that's a must-have document.
upvoted 0 times
Alica
21 days ago
B) Milestone list
upvoted 0 times
...
Teddy
22 days ago
A) Project scope statement
upvoted 0 times
...
...
Gracia
2 months ago
I disagree, I believe the answer is C) Project schedule network diagrams.
upvoted 0 times
...
Henriette
2 months ago
I think the answer is B) Milestone list.
upvoted 0 times
...

Save Cancel