You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are
currently 20 percent complete with this project, though you should be 25 percent complete with the
project work. The project has consumed $595,000 of the project budget to date. Management has
asked you, based on the current project performance, what the project's estimate to complete will
be considering the current project schedule variance. What is the ETC for this project?
The estimate to complete wants to know how much more money the project will need
to complete its objectives.
The estimate to complete (ETC) is the expected cost needed to complete all the remaining work for a
scheduled activity, a group of activities,
or the project. ETC helps project managers predict what the final cost of the project will be upon
completion. The formula for the ETC is EAC-
AC. The EAC is BAC/CPI.
Answer option A is incorrect. This is the estimate at completion based on the current project
performance.
Answer option C is incorrect. This is the current schedule variance.
Answer option B is incorrect. 1.02 is the to-complete performance index based on the BAC.
Thad
10 months agoEliseo
11 months agoAmmie
11 months agoJohana
11 months agoHerman
11 months agoIsaac
11 months agoLewis
11 months agoLeanna
11 months agoKallie
11 months agoCarissa
12 months agoGearldine
12 months agoFrancene
12 months ago