You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?
Risk activities are not part of the schedule data. Risk is documented in the risk register,
and monitored and controlled throughout the project.
In some instances, risk may be part of the activity attributes. The schedule data includes the
schedule milestones, schedule activities, activity
attributes, and the assumptions and constraints.
The schedule data includes the schedule activities, schedule milestones, activity attributes, and
documentation of all known assumptions and
constraints. The sum of additional data varies by application area. The schedule data commonly
supplied as supporting details includes:
Resource requirement by time period, frequently in the category of histogram
Alternative schedules, such as best case or worst case, or resource leveled, with or without imposed
dates
Scheduling of contingency reserves
Answer option D is incorrect. Schedule milestones are part of the schedule data.
a
Answer option B is incorrect. Schedule activities are part of the schedule data.
Answer option C is incorrect. Activity attributes are part of the schedule data.
Tequila
10 months agoNancey
10 months agoStanton
10 months agoCherri
10 months agoTawna
11 months agoVerda
11 months agoCrista
11 months agoKarl
11 months agoCarrol
11 months agoVeronique
11 months agoLeana
11 months agoSalena
11 months agoPaulina
11 months agoWendell
12 months agoMing
12 months agoMuriel
12 months ago