Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 85 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 85
Topic #: 5
[All PMI-SP Questions]

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: B, C

According to the scenario, you can use the following inputs in order to generate

performance reports:

WPI: Work performance information is the data gathered on the status of the project schedule

activities that are performed to

accomplish the project work. This data is collected as part of the Direct and Manage Project

Execution processes. WPI includes the

following:

Deliverables status

Schedule Progress

Costs incurred

WPM: Work performance measurements are created from the work performance information.

WPMs are an output of Control schedule,

Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs

consist of planned versus actual

performance indicators with respect to scope, schedule, and cost. They are documented and

communicated to the stakeholders and are

used to make project activity metrics, such as the following:

Planned vs. Actual Technical performance and Scope performance

Planned vs. Actual Schedule performance

Planned vs. Actual Cost performance

Answer option A is incorrect. Variance analysis is an after-look at what caused a difference between

the baseline and the actual performance.

It is one of the tools and techniques used for report performance.

Answer option D is incorrect. Change requests are requests to expand or reduce the project scope,

modify policies, processes, plans, or

procedures, modify costs or budgets or revise schedules. These requests for a change can be direct

or indirect, externally or internally

initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that

only formally documented requested

changes are processed and only approved change requests are implemented.


Contribute your Thoughts:

Lindsey
5 days ago
Maybe the project manager just has a magic 8-ball they use to develop the schedule. That would explain a lot!
upvoted 0 times
...
Regenia
26 days ago
Wait, if the project scope statement isn't an input, how are we supposed to know what tasks to schedule? This question is making my head spin!
upvoted 0 times
Lorean
11 days ago
A) Resource calendars
upvoted 0 times
...
Celeste
15 days ago
A) Resource calendars
upvoted 0 times
...
...
Sherrell
29 days ago
Ah, I've got it! D) Project scope statement must be the answer. You can't develop a schedule without knowing the scope of the project. Easy peasy!
upvoted 0 times
...
Floyd
1 months ago
Hmm, this is a tricky one. I'm tempted to say A) Resource calendars is not an input, but that feels too obvious. Let me think about this some more.
upvoted 0 times
...
Elizabeth
1 months ago
I agree, D) has to be the correct answer. The project scope statement is fundamental to creating the schedule.
upvoted 0 times
...
Glen
1 months ago
D) Project scope statement seems like an obvious input to the Develop Schedule process. It defines the work that needs to be done, so how could it not be an input?
upvoted 0 times
C) Activity list
upvoted 0 times
...
Annabelle
1 days ago
B) Schedule data
upvoted 0 times
...
Joanne
4 days ago
A) Resource calendars
upvoted 0 times
...
...
Renato
2 months ago
I'm not sure about this one. Can someone explain why the project scope statement is not needed for developing the project schedule?
upvoted 0 times
...
Earnestine
2 months ago
I agree with Rupert. The project scope statement is not an input to the Develop Schedule process.
upvoted 0 times
...
Rupert
2 months ago
I think the answer is D) Project scope statement.
upvoted 0 times
...

Save Cancel