PMI-SP Exam - Topic 5 Question 85 Discussion

Posted by Shay on Aug 26, 2024 at 05:31 AM

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

Suggested Answer: B, C

According to the scenario, you can use the following inputs in order to generate

performance reports:

WPI: Work performance information is the data gathered on the status of the project schedule

activities that are performed to

accomplish the project work. This data is collected as part of the Direct and Manage Project

Execution processes. WPI includes the

following:

Deliverables status

Schedule Progress

Costs incurred

WPM: Work performance measurements are created from the work performance information.

WPMs are an output of Control schedule,

Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs

consist of planned versus actual

performance indicators with respect to scope, schedule, and cost. They are documented and

communicated to the stakeholders and are

used to make project activity metrics, such as the following:

Planned vs. Actual Technical performance and Scope performance

Planned vs. Actual Schedule performance

Planned vs. Actual Cost performance

Answer option A is incorrect. Variance analysis is an after-look at what caused a difference between

the baseline and the actual performance.

It is one of the tools and techniques used for report performance.

Answer option D is incorrect. Change requests are requests to expand or reduce the project scope,

modify policies, processes, plans, or

procedures, modify costs or budgets or revise schedules. These requests for a change can be direct

or indirect, externally or internally

initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that

only formally documented requested

changes are processed and only approved change requests are implemented.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
39 comments · newest first
ER
Ernie 11 months ago
I doubt that, seems like it should be included!
JA
Jamey 11 months ago
Wait, is the Project scope statement really not an input?
YU
Yuonne 12 months ago
Isn't the Activity list always needed?
LU
Lucina 12 months ago
I think Schedule data is crucial too.
NO
Noah 1 year ago
Resource calendars are definitely an input.
EL
Elbert 1 year ago
I’m leaning towards schedule data being the odd one out, but I might be mixing it up with another process.
GR
Graciela 1 year ago
I practiced a similar question where we had to identify inputs, and I feel like resource calendars were included in that one.
LO
Lovetta 1 year ago
I think the project scope statement is definitely an input, but I can't recall if the schedule data is also one.
PU
Pura 1 year ago
I remember we discussed the inputs for the Develop Schedule process, but I'm not entirely sure which one doesn't belong.
AL
Alexia 1 year ago
Okay, let's think this through. The project scope statement is definitely an input, so that can't be the answer. I'll focus on the other options.
MA
Mable 1 year ago
Hmm, I'm a bit unsure about this one. I need to make sure I understand all the inputs to the Develop Schedule process.
MA
Martin 1 year ago
This question seems straightforward. I'll review the inputs listed and eliminate the one that doesn't belong.
BL
Blondell 1 year ago
I've got this! The project scope statement is not an input to the Develop Schedule process. The other options are all valid inputs.
KE
Keva 1 year ago
I feel like it could also be in the development stage, but that seems more about content creation rather than audience targeting.
LI
Lindsey 1 year ago
Maybe the project manager just has a magic 8-ball they use to develop the schedule. That would explain a lot!
CA
Carlota 1 year ago
↳ replying to Lindsey
C) Activity list
CO
Corazon 1 year ago
↳ replying to Lindsey
B) Schedule data
MA
Marilynn 1 year ago
↳ replying to Lindsey
D) Project scope statement
GW
Gwenn 1 year ago
↳ replying to Lindsey
A) Resource calendars
CH
Chan 1 year ago
↳ replying to Lindsey
C) Activity list
BL
Blair 1 year ago
↳ replying to Lindsey
B) Schedule data
PE
Pete 1 year ago
↳ replying to Lindsey
A) Resource calendars
RE
Regenia 2 years ago
Wait, if the project scope statement isn't an input, how are we supposed to know what tasks to schedule? This question is making my head spin!
RO
Roselle 1 year ago
↳ replying to Regenia
C) Activity list
NA
Natalie 1 year ago
↳ replying to Regenia
B) Schedule data
BE
Becky 1 year ago
↳ replying to Regenia
C) Activity list
VE
Veronica 1 year ago
↳ replying to Regenia
B) Schedule data
LO
Lorean 1 year ago
↳ replying to Regenia
A) Resource calendars
CE
Celeste 2 years ago
↳ replying to Regenia
A) Resource calendars
SH
Sherrell 2 years ago
Ah, I've got it! D) Project scope statement must be the answer. You can't develop a schedule without knowing the scope of the project. Easy peasy!
FL
Floyd 2 years ago
Hmm, this is a tricky one. I'm tempted to say A) Resource calendars is not an input, but that feels too obvious. Let me think about this some more.
EL
Elizabeth 2 years ago
I agree, D) has to be the correct answer. The project scope statement is fundamental to creating the schedule.
GL
Glen 2 years ago
D) Project scope statement seems like an obvious input to the Develop Schedule process. It defines the work that needs to be done, so how could it not be an input?
QU
Quentin 1 year ago
↳ replying to Glen
C) Activity list
AN
Annabelle 1 year ago
↳ replying to Glen
B) Schedule data
JO
Joanne 1 year ago
↳ replying to Glen
A) Resource calendars
RE
Renato 2 years ago
I'm not sure about this one. Can someone explain why the project scope statement is not needed for developing the project schedule?
EA
Earnestine 2 years ago
I agree with Rupert. The project scope statement is not an input to the Develop Schedule process.
RU
Rupert 2 years ago
I think the answer is D) Project scope statement.