PMI-SP Exam - Topic 5 Question 8 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 8
Topic #: 5
[All PMI-SP Questions]

You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?

Show Suggested Answer Hide Answer
Suggested Answer: D

Fast tracking allows entire phases of the project to overlap and this action does

increase risks. This is an approach that you would want to

avoid in your project.

Answer option B is incorrect. Crashing adds labor to the project and typically drives project costs.

Answer option A is incorrect. The critical chain method considers the availability of project resources

as part of its network diagramming

technique.

Answer option C is incorrect. Lead time allows project activities to overlap and may introduce

project risks, but not to the extent of using fast

tracking.


Contribute your Thoughts:

0/2000 characters
Wenona
4 months ago
Totally agree, crashing is a big risk factor!
upvoted 0 times
...
Ryan
4 months ago
Wait, can we really make that much bonus? Sounds too good to be true!
upvoted 0 times
...
Juliana
4 months ago
Adding leads can also complicate things.
upvoted 0 times
...
Ciara
4 months ago
I think fast tracking is riskier than crashing.
upvoted 0 times
...
Malcom
4 months ago
Crashing definitely increases risk!
upvoted 0 times
...
Teddy
5 months ago
I think crashing is definitely the most aggressive approach, and it usually raises the risk level. I saw a similar question in our practice exam.
upvoted 0 times
...
Lorrine
5 months ago
I feel like adding leads could also increase risk, but I’m not confident. I remember it being discussed in class, but I can't recall the details.
upvoted 0 times
...
Theola
5 months ago
Fast tracking sounds familiar, and I think it can lead to more risks because tasks overlap. I practiced a question like this in our last review session.
upvoted 0 times
...
Lynna
5 months ago
I remember studying the different scheduling techniques, but I'm not entirely sure which one increases risk the most. I think crashing might be risky, but I need to double-check.
upvoted 0 times
...
Irene
5 months ago
I'm feeling a bit lost on this one. There are a few options presented, but I'm not sure which one is the best fit. I'll have to read the question again and try to think through the different features more carefully.
upvoted 0 times
...
Norah
5 months ago
Hmm, not sure I'm following the instructions completely. Hiding columns can be a bit tricky, but I'll give it my best shot and try to work through it step-by-step.
upvoted 0 times
...
Teddy
5 months ago
I'm a bit confused by the wording here. I'll need to re-read the question and options a few times to make sure I understand what they're asking.
upvoted 0 times
...
Dorathy
5 months ago
This one seems straightforward, I'm pretty confident I can figure it out.
upvoted 0 times
...