PMI Exam PMI-SP Topic 5 Question 68 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 68
Topic #: 5
[All PMI-SP Questions]

Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Cherry
12 days ago
Ah, C) Fragment network - that's what they're teaching us these days. Gotta stay on top of the project management lingo, you know?
upvoted 0 times
...
Ricarda
14 days ago
Haha, I almost went with B) Hanger. Guess I should have paid more attention in class! C) Fragment network is the way to go.
upvoted 0 times
...
Paris
15 days ago
Definitely C) Fragment network. It's a common practice to use a part of an existing template, so this makes the most sense.
upvoted 0 times
...
Christoper
19 days ago
I think the correct answer is C) Fragment network. Using a portion of a network template diagram seems to fit this term perfectly.
upvoted 0 times
Lashanda
7 days ago
I agree, C) Fragment network makes sense in this context.
upvoted 0 times
...
...
Felicia
1 months ago
I'm not sure, but I think it could also be Analogous. It seems like a common practice in project management.
upvoted 0 times
...
Deane
1 months ago
I agree with Tori, it makes sense to use a portion of a network template for similar projects.
upvoted 0 times
...
Tori
1 months ago
I think the term is Fragment network.
upvoted 0 times
...
Cecily
1 months ago
I'm not sure, but it makes sense that it would be Fragment network since it's just a part of the template.
upvoted 0 times
...
Luisa
2 months ago
I agree with Nichelle, using a portion of a network template is called Fragment network.
upvoted 0 times
...
Nichelle
2 months ago
I think the term is Fragment network.
upvoted 0 times
...