Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Shawnee
6 months agoEloisa
6 months agoBlair
7 months agoTasia
7 months agoKendra
7 months agoMerlyn
7 months agoDarci
8 months agoCarmelina
8 months agoNobuko
8 months agoGertude
8 months agoTelma
8 months agoLauna
8 months agoGolda
8 months agoHana
8 months agoGail
8 months agoCraig
8 months agoErnest
8 months agoGeorgiann
8 months agoShonda
8 months agoCherry
1 year agoRicarda
1 year agoParis
1 year agoOra
11 months agoAmira
11 months agoLavina
12 months agoChristoper
1 year agoCarmen
1 year agoRoyal
1 year agoLashanda
1 year agoFelicia
1 year agoDeane
1 year agoTori
1 year agoCecily
1 year agoLuisa
1 year agoNichelle
1 year ago