You work as a scheduler for your organization. You are developing a schedule and its constraints for
the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT
an input to the schedule development process?
The WBS is not an input, directly, to the develop schedule process. Technically, you will
need the scope baseline, which does include the WBS.
The inputs in developing a schedule process are of nine types, which are as follows:
Activity list
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Enterprize environmental factors
Organization process assets
Ronnie
9 months agoAdela
9 months agoReid
9 months agoMoon
9 months agoSylvia
9 months agoAnissa
10 months agoShizue
10 months agoJenifer
10 months agoNieves
10 months agoStaci
10 months agoRaylene
10 months agoRicki
10 months agoTheresia
10 months ago