You work as a scheduler for your organization. You are developing a schedule and its constraints for
the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT
an input to the schedule development process?
The WBS is not an input, directly, to the develop schedule process. Technically, you will
need the scope baseline, which does include the WBS.
The inputs in developing a schedule process are of nine types, which are as follows:
Activity list
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Enterprize environmental factors
Organization process assets
Ronnie
10 months agoAdela
11 months agoReid
11 months agoMoon
11 months agoSylvia
11 months agoAnissa
11 months agoShizue
11 months agoJenifer
11 months agoNieves
11 months agoStaci
12 months agoRaylene
12 months agoRicki
12 months agoTheresia
12 months ago