You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is
scheduled to last for three years. Your project is currently forty percent complete though it should
be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.
Management needs a performance report regarding the NHQ project. Management is concerned
that this project will be over budget upon completion. Management would like to create a report
telling them how much more the project will need to complete. What value should you tell
management?
The project will need $787,504 more to complete. This formula, the estimate to
complete, is estimate at completion minus the actual costs.
Here,
CPI = EV/AC =(0.40*1,258,456)/525000= 0.95882, and
ETC = EAC - AC
= (BAC/CPI) - AC
=(1,258,456/0.95882) - 525000
= 1,312,504- 525000
= 787,504
The estimate to complete (ETC) is the expected cost needed to complete all the remaining work for a
scheduled activity, a group of activities,
or the project. ETC helps project managers predict what the final cost of the project will be upon
completion. The formula for the ETC is EAC-
AC. The EAC is BAC/CPI.
Answer option C is incorrect. This is the estimate at completion.
Answer option A is incorrect. This is the planned value.
Answer option D is incorrect. This is not a valid value based on the current project performance.
Janessa
10 months agoLeonardo
11 months agoGoldie
11 months agoDulce
11 months agoBobbie
11 months agoWinfred
11 months agoLeonie
11 months agoVerdell
11 months agoAnabel
11 months agoShizue
12 months agoOlive
12 months agoKenneth
12 months agoLettie
12 months ago