Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Leslee
6 days agoNell
11 days agoLashaunda
17 days agoLorrie
22 days agoArlean
27 days agoTrina
1 month agoLarue
3 months agoMelodie
3 months agoClorinda
4 months agoAlishia
4 months agoGalen
4 months agoLou
4 months ago