Examine the figure given below: Which path is considered the critical path?
The critical path is the path in the project network diagram with the longest duration. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). In this instance path ACGIJ is the longest as it takes 23 days.
Answer options C and D are incorrect. These paths take 13 days. Answer option A is incorrect. This path only takes 19 days.
Josephine
5 months agoMollie
6 months agoLorita
6 months agoIrma
6 months agoAleisha
6 months agoLashawn
6 months agoJuan
7 months agoJess
7 months agoPhuong
7 months agoHerman
7 months agoBelen
8 months agoVincenza
8 months agoCoral
8 months agoMing
8 months agoYolando
10 months agoKatina
8 months agoGlory
10 months agoMaryann
10 months agoSusana
11 months agoMollie
10 months agoDenae
10 months agoAntonio
11 months agoGraciela
11 months agoCathern
10 months agoElenor
10 months agoLisbeth
10 months agoFidelia
10 months agoRikki
10 months agoJose
11 months agoAlverta
11 months agoJose
12 months ago