Examine the figure given below: Which path is considered the critical path?
The critical path is the path in the project network diagram with the longest duration. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). In this instance path ACGIJ is the longest as it takes 23 days.
Answer options C and D are incorrect. These paths take 13 days. Answer option A is incorrect. This path only takes 19 days.
Josephine
9 months agoMollie
9 months agoLorita
9 months agoIrma
9 months agoAleisha
10 months agoLashawn
10 months agoJuan
10 months agoJess
10 months agoPhuong
11 months agoHerman
11 months agoBelen
11 months agoVincenza
11 months agoCoral
11 months agoMing
11 months agoYolando
1 year agoKatina
12 months agoGlory
1 year agoMaryann
1 year agoSusana
1 year agoMollie
1 year agoDenae
1 year agoAntonio
1 year agoGraciela
1 year agoCathern
1 year agoElenor
1 year agoLisbeth
1 year agoFidelia
1 year agoRikki
1 year agoJose
1 year agoAlverta
1 year agoJose
1 year ago