You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?
Stakeholders are interviewed and can help identify other stakeholders that should be
included in the project communications.
Answer option B is incorrect. According to the PMBOK, this is not the best answer.
Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by
it.
Answer option C is incorrect. Project customers are stakeholders.
Judy
10 months agoElly
10 months agoHana
10 months agoAnnmarie
10 months agoDana
11 months agoEric
11 months agoBernardine
11 months agoRaymon
11 months agoSharmaine
11 months agoHoney
11 months agoLouvenia
11 months agoLouvenia
11 months agoMariko
11 months agoDorothy
1 year agoEmile
1 year agoPeggie
1 year agoLavelle
1 year agoTy
1 year agoMari
1 year agoMelodie
1 year agoDeeanna
1 year agoFrance
1 year agoRose
1 year agoLenna
1 year agoTaryn
1 year agoKris
1 year agoLaurel
1 year agoClay
1 year agoCordie
1 year agoBelen
1 year agoLoren
1 year agoStephane
1 year agoColetta
1 year agoArthur
1 year agoDeeanna
1 year agoClare
1 year agoSuzi
1 year agoLinwood
1 year agoColby
1 year ago