Examine the figure given below.

In this project network diagram, what is the total float for Activity I?
Suggested Answer: A
Get Premium PMI-SP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
21 comments · newest first
RO
Roxane
11 months ago
Pretty sure it's zero, but I could be wrong.
CE
Celeste
11 months ago
Wait, how can it be one? That doesn't add up!
PA
Paz
12 months ago
I'm leaning towards five, seems like a lot of flexibility.
CA
Candida
12 months ago
I think it's zero, no wiggle room there!
SY
Sylvie
1 year ago
Total float for Activity I is definitely three.
RI
Rima
1 year ago
I feel like the answer might be five, but I need to double-check the dependencies in the diagram to be sure.
CH
Charolette
1 year ago
I practiced a question like this where the float was zero, but I’m not confident if that applies here too.
MA
Mabel
1 year ago
I think total float is the amount of time an activity can be delayed without affecting the project. I just can’t recall the specifics for Activity I.
ZE
Zena
1 year ago
I remember calculating total float in a similar question, but I’m not sure if I got the formula right for this one.
RO
Roslyn
1 year ago
No problem, I've got this. I just need to identify the total float based on the start and end dates for Activity I.
PA
Pansy
1 year ago
This looks tricky, but I think I can figure it out if I focus on the critical path and work backwards.
BE
Benedict
1 year ago
Hmm, let me think through this step-by-step. I'll need to analyze the project network diagram and calculate the total float for Activity I.
CA
Cassie
1 year ago
Okay, I see the diagram and the options. I'm a bit unsure, but I'll give it my best shot.
FR
Freeman
1 year ago
I'm a little confused on this one. Is it the security policy, security protection, or security profile that the interface needs to be assigned to? I'll have to review my notes to make sure I understand the right configuration for an interface to process traffic.
PA
Paris
1 year ago
I think the best approach here is to make sure the analyst has regular pairing meetings with the other team member throughout the task execution. That way, they can learn from the expert and get the support they need.
JI
Jillian
2 years ago
Interesting. I guess I'll go with C) Five. It's just a gut feeling.
NI
Nina
2 years ago
I'm leaning towards B) Zero. It seems like there's no extra time for Activity I.
JO
Jonell
2 years ago
I disagree. I believe the answer is D) One, but I'm not sure.
EL
Elise
2 years ago
I think the answer is A) Three.
MI
Micaela
2 years ago
Yeah, it's tricky. Especially calculating the float for Activity I.
JI
Jillian
3 years ago
Did you see the question about the project network diagram?