Examine the figure given below.

In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Roxane
10 months agoCeleste
10 months agoPaz
10 months agoCandida
10 months agoSylvie
11 months agoRima
11 months agoCharolette
11 months agoMabel
11 months agoZena
11 months agoRoslyn
11 months agoPansy
11 months agoBenedict
11 months agoCassie
12 months agoFreeman
12 months agoParis
12 months agoJillian
2 years agoNina
2 years agoJonell
2 years agoElise
2 years agoMicaela
2 years agoJillian
2 years ago