New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 4 Question 62 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 62
Topic #: 4
[All PMI-SP Questions]

If you are the project manager of the BNQ Project and you add "waiting time" between two

activities, then what have you added in the project?

Show Suggested Answer Hide Answer
Suggested Answer: A

Lag time is positive time that requires the successor activity to wait for a defined

amount of time, such as three days, before it can begin. Lag

time does not change the task relationship, but requires a 'waiting time' before the starting of the

activity can begin.

A lag time is a delay between the predecessor and the successor tasks. Sometimes it may be needed

to schedule a delay between the

predecessor and the successor tasks. For example, if two coats of paint are required to paint a car,

then the final coat should be applied only

when the first coat dries. This delay is known as the lag time. The lag time is entered as a positive

value. The lag time can be entered as a

duration or as a percentage of the predecessor's task duration. It is entered on the Predecessor tab

in the Task Information dialog box.

Answer option D is incorrect. Float is a natural event that is discovered through the forward pass

when using the critical path method. Float

cannot be arbitrarily added as lag.

Answer option C is incorrect. Lead time actually brings activities closer together and causes them, in

some cases, to overlap.

Answer option B is incorrect. Management reserve is a pool of time allotted for unscheduled

changes and events that affect the project

duration.


Contribute your Thoughts:

0/2000 characters
Johnetta
4 months ago
Management reserve is a different concept altogether.
upvoted 0 times
...
Karina
4 months ago
100% agree, it's lag time for sure!
upvoted 0 times
...
Miriam
4 months ago
Wait, are we sure it's not lead time?
upvoted 0 times
...
Casandra
4 months ago
I thought it was float, but lag makes sense.
upvoted 0 times
...
Thaddeus
4 months ago
Definitely added lag time!
upvoted 0 times
...
Arminda
5 months ago
Float is usually about flexibility in scheduling, but I don't think that's what we're adding here. Lag time feels like the best answer.
upvoted 0 times
...
Margarita
5 months ago
I feel like lead time is more about starting activities earlier, so it can't be that. Lag time seems more likely.
upvoted 0 times
...
Albina
5 months ago
I’m not entirely sure, but I remember something about management reserves being related to delays. Could that be it?
upvoted 0 times
...
Raul
5 months ago
I think adding "waiting time" means we’re looking at lag time, right? That sounds familiar from the practice questions.
upvoted 0 times
...
Herminia
5 months ago
This seems straightforward. I'd go with option A or B to make the Folder class implement the necessary interface, and then add the close() method in option D or E. That should be the simplest way to get the desired output.
upvoted 0 times
...
Casandra
5 months ago
I'm a bit confused by this question. Deleting cases as new ones are created? That doesn't sound like a good idea at all. I think I'll go with optimizing queries and the data retention plan - those seem like the safest bets.
upvoted 0 times
...
Corazon
5 months ago
Okay, the key here is that the architect needs a centralized solution without creating new catalogs or device collections. That rules out some of the options like PXE.
upvoted 0 times
...

Save Cancel