Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 4 Question 62 Discussion

Posted by Ty on Dec 11, 2022 at 01:28 PM

If you are the project manager of the BNQ Project and you add "waiting time" between two

activities, then what have you added in the project?

Suggested Answer: A

Lag time is positive time that requires the successor activity to wait for a defined

amount of time, such as three days, before it can begin. Lag

time does not change the task relationship, but requires a 'waiting time' before the starting of the

activity can begin.

A lag time is a delay between the predecessor and the successor tasks. Sometimes it may be needed

to schedule a delay between the

predecessor and the successor tasks. For example, if two coats of paint are required to paint a car,

then the final coat should be applied only

when the first coat dries. This delay is known as the lag time. The lag time is entered as a positive

value. The lag time can be entered as a

duration or as a percentage of the predecessor's task duration. It is entered on the Predecessor tab

in the Task Information dialog box.

Answer option D is incorrect. Float is a natural event that is discovered through the forward pass

when using the critical path method. Float

cannot be arbitrarily added as lag.

Answer option C is incorrect. Lead time actually brings activities closer together and causes them, in

some cases, to overlap.

Answer option B is incorrect. Management reserve is a pool of time allotted for unscheduled

changes and events that affect the project

duration.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
JO
Johnetta 12 months ago
Management reserve is a different concept altogether.
KA
Karina 1 year ago
100% agree, it's lag time for sure!
MI
Miriam 1 year ago
Wait, are we sure it's not lead time?
CA
Casandra 1 year ago
I thought it was float, but lag makes sense.
TH
Thaddeus 1 year ago
Definitely added lag time!
AR
Arminda 1 year ago
Float is usually about flexibility in scheduling, but I don't think that's what we're adding here. Lag time feels like the best answer.
MA
Margarita 1 year ago
I feel like lead time is more about starting activities earlier, so it can't be that. Lag time seems more likely.
AL
Albina 1 year ago
I’m not entirely sure, but I remember something about management reserves being related to delays. Could that be it?
RA
Raul 1 year ago
I think adding "waiting time" means we’re looking at lag time, right? That sounds familiar from the practice questions.
HE
Herminia 1 year ago
This seems straightforward. I'd go with option A or B to make the Folder class implement the necessary interface, and then add the close() method in option D or E. That should be the simplest way to get the desired output.
CA
Casandra 1 year ago
I'm a bit confused by this question. Deleting cases as new ones are created? That doesn't sound like a good idea at all. I think I'll go with optimizing queries and the data retention plan - those seem like the safest bets.
CO
Corazon 1 year ago
Okay, the key here is that the architect needs a centralized solution without creating new catalogs or device collections. That rules out some of the options like PXE.
0/2000 characters

Save Cancel