New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 4 Question 28 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 28
Topic #: 4
[All PMI-SP Questions]

You are the project manager for your organization. Your current project has a schedule variance of -

$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project

performance?

Show Suggested Answer Hide Answer
Suggested Answer: D

A schedule variance is found by subtracting the planned value from the earned value. A

-$37,500 schedule variance is considerable for most

projects, but combined with a schedule that is six percent off schedule is more serious. The size of

the project, however, and the defined

project budget, needs to be determined to evaluate how serious the variance is.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option B is incorrect. This project is not performing well based on the given information.

Answer option A is incorrect. This project is likely to be late, but we do not know how costs are

performing in this question.

Answer option C is incorrect. There is not enough information to determine how well the project is

performing from this answer.


Contribute your Thoughts:

0/2000 characters
Denna
4 months ago
Six percent off schedule sounds serious, we need to address this!
upvoted 0 times
...
Felicitas
4 months ago
I think the planned value is around $600,000, right?
upvoted 0 times
...
Mitsue
4 months ago
Wait, how can it be performing well with those stats?
upvoted 0 times
...
Iola
4 months ago
Totally agree, those numbers aren't good!
upvoted 0 times
...
Iluminada
4 months ago
Looks like the project is behind schedule and over budget.
upvoted 0 times
...
Marci
5 months ago
I thought the planned value was calculated differently, so I'm not convinced about option C being true. It seems like we need to focus on the schedule variance instead.
upvoted 0 times
...
Casandra
5 months ago
I practiced similar questions, and I recall that a SPI of 0.94 suggests we're falling behind, which aligns with option A.
upvoted 0 times
...
Edwin
5 months ago
I'm not entirely sure, but I think a schedule performance index below 1 means we're not performing well. That could point to option D being the right choice.
upvoted 0 times
...
Aracelis
5 months ago
I remember that a negative schedule variance usually indicates that we're behind schedule, so I think option A might be correct.
upvoted 0 times
...
Terrilyn
5 months ago
This question seems straightforward - I think the key is to focus on the "strategy level" part and consider what would help avoid waste at that high level. Option B about having a shared understanding of goals and priorities seems like the best fit.
upvoted 0 times
...
Shizue
5 months ago
I'm a little confused by this question. I know the nmGenBootStartupProps command is related to Node Manager, but I'm not sure about the specifics of what it does. I'll have to carefully read through the options and try to eliminate the ones that don't sound right.
upvoted 0 times
...
Dino
5 months ago
I'm not entirely sure, but ignoring the problem sounds risky since it could impact performance later, right?
upvoted 0 times
...

Save Cancel