You are the project manager for your organization. You are coaching Allen, a junior project manager,
on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?
The critical path is discovered by summing the duration of each activity node in each
chain of activities in the project network diagram. In this
figure, the critical path is ACFGJ, which is 26 days, the longest chain of activities in the project.
Answer option A is incorrect. This path's duration is 22 days.
Answer option D is incorrect. This path's duration is 23 days.
Answer option C is incorrect. This path's duration is 15 days.
Alline
9 months agoLoreta
9 months agoLacey
9 months agoMabelle
9 months agoLon
9 months agoJohnna
10 months agoTennie
10 months agoPamela
10 months agoAllene
10 months agoTy
10 months agoKerrie
10 months agoLouis
10 months agoJanna
10 months ago