You are the project manager for your organization. You are coaching Allen, a junior project manager,
on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?
The critical path is discovered by summing the duration of each activity node in each
chain of activities in the project network diagram. In this
figure, the critical path is ACFGJ, which is 26 days, the longest chain of activities in the project.
Answer option A is incorrect. This path's duration is 22 days.
Answer option D is incorrect. This path's duration is 23 days.
Answer option C is incorrect. This path's duration is 15 days.
Alline
10 months agoLoreta
11 months agoLacey
11 months agoMabelle
11 months agoLon
11 months agoJohnna
11 months agoTennie
11 months agoPamela
11 months agoAllene
11 months agoTy
12 months agoKerrie
12 months agoLouis
12 months agoJanna
12 months ago