Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 4 Question 117 Discussion

Posted by Helaine on May 30, 2026 at 03:42 AM

You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

Suggested Answer: C

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis

to predict future performance. CPI is the

ratio of earned value to actual cost. The CPI is calculated based on the following formula:

CPI = Earned Value (EV) / Actual Cost (AC)

If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The CPI value of 1 indicates that the project is right on target. In this instance it's

$350,000 divided by $425,000 for a CPI

of .82.

Answer option B is incorrect. $350,000 is the earned value of the project.

Answer option A is incorrect. -$75,000 is the cost variance for the project.

Answer option D is incorrect. -$187,500 is the predicted variance at the completion of the project.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
22 comments · newest first
BR
Breana 22 days ago
Let's hope we get it right!
CH
Charlie 27 days ago
Management will like this answer.
LU
Luke 1 month ago
Me too! Option C seems right.
BR
Breana 1 month ago
I feel confident about this one!
CH
Charlie 1 month ago
Which gives us .82.
LU
Luke 2 months ago
So, CPI = $350,000 / $425,000.
BR
Breana 2 months ago
And AC is $425,000.
CH
Charlie 2 months ago
That's $350,000.
LU
Luke 2 months ago
Yes! EV is 40% of $875,000.
BR
Breana 2 months ago
CPI is EV divided by AC, correct?
CH
Charlie 2 months ago
Right! We need to find the earned value.
LU
Luke 3 months ago
I think it's about calculating CPI.
CH
Charlie 3 months ago
This question is tricky.
LU
Luis 3 months ago
Are we sure about those numbers? Seems off!
BU
Burma 3 months ago
Wait, how did we spend that much already?
LO
Lonna 3 months ago
That sounds about right, I agree!
DA
Dahlia 3 months ago
I think it's .82, right?
WI
Willow 4 months ago
CPI is calculated as EV/AC.
JE
Jeannetta 4 months ago
I think the CPI should be around .82 based on my calculations, but I need to double-check my math on the actual costs.
GR
Graciela 4 months ago
I feel like I might be mixing up the formulas, but isn't the earned value just the budget times the percent complete?
GW
Gwenn 4 months ago
I remember a similar question where we had to find the CPI. If I recall correctly, it's earned value divided by actual cost.
KA
Kattie 4 months ago
I think the cost performance index is calculated using earned value and actual cost, but I'm not entirely sure how to apply it here.
0/2000 characters

Save Cancel