Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 98 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 98
Topic #: 3
[All PMI-SP Questions]

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

Show Suggested Answer Hide Answer
Suggested Answer: D

According to the question, you have to use the estimating technique that has a higher

degree of accuracy. The most accurate estimating

technique is bottom-up estimating.

What is bottom-up estimating?

Bottom-up is a cost estimating technique that involves estimating the cost of individual work

packages or schedule

activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher

levels for total project

estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up

estimating provides a

higher degree of accuracy, provided the estimates at the work package level are accurate.

Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques

use top-down estimation model. These

are less accurate than the bottom-up estimation.

What is analogous estimating?

Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget,

and duration or

measures of scale such as size, weight, and complexity from a previous, similar activity as the basis

for estimation of the

same parameter for a future activity. It is a top-down estimating technique and is a form of expert

judgment. It provides a

lower degree of accuracy than other estimating techniques. This technique is primarily used when

there is a limited amount

of detailed information about the project or program.

What is parametric modeling?

Parametric modeling is an estimating technique that uses parameters, or project characteristics, to

forecast project costs.

It involves a top-down approach and is similar but more accurate than analogous estimating. It uses

historical data and

other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and

duration.


Contribute your Thoughts:

Simona
2 days ago
Resource calendar conflict, for sure. Tim's a busy guy, ain't he? Beth's got her work cut out for her trying to wrangle his time.
upvoted 0 times
...
Yvonne
3 days ago
Hmm, I was initially thinking B) Matrix network, but I think Johnson, Thersa, and Maybelle have it right. This is a resource calendar conflict, plain and simple.
upvoted 0 times
...
Maybelle
12 days ago
This is a tricky one, but I'm going with A) Resource calendar conflict as well. The fact that Tim is already booked on other projects and unavailable for Beth's project activities is the key point here.
upvoted 0 times
...
Thersa
14 days ago
I agree with Johnson. This is definitely a resource calendar conflict. Beth doesn't have access to Tim when she needs him, which is a classic example of this issue.
upvoted 0 times
...
Johnson
1 months ago
I think the answer is A) Resource calendar conflict. It's clear that Tim, the highly-skilled resource, is already scheduled on other projects, which is causing a conflict with Beth's project needs.
upvoted 0 times
Arthur
3 days ago
Actually, it's more about Tim's availability conflicting with the project schedule, so A) Resource calendar conflict is the right answer.
upvoted 0 times
...
Shad
7 days ago
D) Activity resource requirements
upvoted 0 times
...
Emelda
14 days ago
Yes, that's correct. Tim's availability is conflicting with Beth's project timeline.
upvoted 0 times
...
Rodney
18 days ago
A) Resource calendar conflict
upvoted 0 times
...
...
Eileen
2 months ago
But could it also be D) Activity resource requirements, since Tim is a key resource for the project?
upvoted 0 times
...
Elena
2 months ago
I agree with Craig, because Tim's availability is conflicting with the project schedule.
upvoted 0 times
...
Craig
2 months ago
I think the answer is A) Resource calendar conflict.
upvoted 0 times
...

Save Cancel