Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 3 Question 98 Discussion

Posted by Florinda on Mar 07, 2025 at 07:14 PM

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

Suggested Answer: D

According to the question, you have to use the estimating technique that has a higher

degree of accuracy. The most accurate estimating

technique is bottom-up estimating.

What is bottom-up estimating?

Bottom-up is a cost estimating technique that involves estimating the cost of individual work

packages or schedule

activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher

levels for total project

estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up

estimating provides a

higher degree of accuracy, provided the estimates at the work package level are accurate.

Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques

use top-down estimation model. These

are less accurate than the bottom-up estimation.

What is analogous estimating?

Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget,

and duration or

measures of scale such as size, weight, and complexity from a previous, similar activity as the basis

for estimation of the

same parameter for a future activity. It is a top-down estimating technique and is a form of expert

judgment. It provides a

lower degree of accuracy than other estimating techniques. This technique is primarily used when

there is a limited amount

of detailed information about the project or program.

What is parametric modeling?

Parametric modeling is an estimating technique that uses parameters, or project characteristics, to

forecast project costs.

It involves a top-down approach and is similar but more accurate than analogous estimating. It uses

historical data and

other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and

duration.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
33 comments · newest first
RE
Rebecka 11 months ago
Seems like a stretch to call it a conflict, but okay.
YO
Yolando 11 months ago
Wow, I didn't realize Tim was the only one who could do that!
DO
Dorinda 11 months ago
I agree, Tim's schedule is packed!
AN
Annmarie 11 months ago
Not so sure, could it be an organizational process asset?
MA
Margot 11 months ago
This is definitely a resource calendar conflict.
LI
Lili 12 months ago
I’m a bit confused; I thought matrix network had to do with team structures. But this situation seems more about scheduling conflicts.
NI
Nicolette 12 months ago
I feel like this is definitely about Tim's availability, so resource calendar conflict makes sense. We discussed this in class.
DI
Diane 1 year ago
I'm not entirely sure, but I remember something about resource allocation issues. Could it be related to activity resource requirements?
EL
Ellsworth 1 year ago
I think this might be a resource calendar conflict since Tim's schedule is already full. It sounds familiar from our practice questions.
DE
Dexter 1 year ago
This is a tricky one, but I'm leaning towards resource calendar conflict. The question seems to be getting at how limited availability of a critical resource can impact a project.
WI
Wilda 1 year ago
Okay, the key here is that Tim is a highly-skilled resource who is already booked on other projects, so Beth can't access him when she needs him. I think that points to a resource calendar conflict.
HU
Huey 1 year ago
Hmm, I'm a bit unsure about the differences between these options. I'll need to carefully read through each one and think about how they relate to the scenario described.
AR
Aretha 1 year ago
This seems like a straightforward question about resource constraints. I'll focus on identifying the key terms and concepts related to resource availability.
SI
Simona 1 year ago
Resource calendar conflict, for sure. Tim's a busy guy, ain't he? Beth's got her work cut out for her trying to wrangle his time.
YV
Yvonne 1 year ago
Hmm, I was initially thinking B) Matrix network, but I think Johnson, Thersa, and Maybelle have it right. This is a resource calendar conflict, plain and simple.
LI
Lillian 1 year ago
↳ replying to Yvonne
Maybe we can try to rearrange Tim's schedule to prioritize our project.
DO
Doretha 1 year ago
↳ replying to Yvonne
We need to find a solution to this resource constraint issue.
AR
Arlean 1 year ago
↳ replying to Yvonne
Yeah, Tim being unavailable due to his other projects is causing a delay.
CA
Carol 1 year ago
↳ replying to Yvonne
I agree, it's definitely a resource calendar conflict.
MA
Maybelle 1 year ago
This is a tricky one, but I'm going with A) Resource calendar conflict as well. The fact that Tim is already booked on other projects and unavailable for Beth's project activities is the key point here.
TH
Thersa 2 years ago
I agree with Johnson. This is definitely a resource calendar conflict. Beth doesn't have access to Tim when she needs him, which is a classic example of this issue.
CA
Carolann 1 year ago
↳ replying to Thersa
But isn't it more about Tim's availability for specific project activities?
GE
Georgiana 1 year ago
↳ replying to Thersa
D) Activity resource requirements
MA
Malcolm 1 year ago
↳ replying to Thersa
Yes, Beth is facing a scheduling issue with Tim.
ST
Stephen 1 year ago
↳ replying to Thersa
A) Resource calendar conflict
JO
Johnson 2 years ago
I think the answer is A) Resource calendar conflict. It's clear that Tim, the highly-skilled resource, is already scheduled on other projects, which is causing a conflict with Beth's project needs.
AR
Arthur 1 year ago
↳ replying to Johnson
Actually, it's more about Tim's availability conflicting with the project schedule, so A) Resource calendar conflict is the right answer.
SH
Shad 1 year ago
↳ replying to Johnson
D) Activity resource requirements
EM
Emelda 2 years ago
↳ replying to Johnson
Yes, that's correct. Tim's availability is conflicting with Beth's project timeline.
RO
Rodney 2 years ago
↳ replying to Johnson
A) Resource calendar conflict
EI
Eileen 2 years ago
But could it also be D) Activity resource requirements, since Tim is a key resource for the project?
EL
Elena 2 years ago
I agree with Craig, because Tim's availability is conflicting with the project schedule.
CR
Craig 2 years ago
I think the answer is A) Resource calendar conflict.
0/2000 characters

Save Cancel