You are the project manager of the GHE Project. You have identified the following risks with the
characteristics as shown in the following figure:

Beth, the project manager, is responsible for communication with all stakeholders. According to the
PMBOK, the project manager occupies the
center of the interactions between stakeholders and the project itself.
Answer option B is incorrect. Sarah may help with the communications, but she is not responsible
for the communications.
Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the
information.
Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for
communicating with the project
stakeholders.