Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 82 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 82
Topic #: 3
[All PMI-SP Questions]

You are the project manager of the GHE Project. You have identified the following risks with the

characteristics as shown in the following figure:

Show Suggested Answer Hide Answer
Suggested Answer: D

Beth, the project manager, is responsible for communication with all stakeholders. According to the

PMBOK, the project manager occupies the

center of the interactions between stakeholders and the project itself.

Answer option B is incorrect. Sarah may help with the communications, but she is not responsible

for the communications.

Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the

information.

Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for

communicating with the project

stakeholders.


Contribute your Thoughts:

Cheryl
2 days ago
I'd go with option E) Throw a dart and see what happens. That's how I usually handle project risks!
upvoted 0 times
...
Cherri
6 days ago
I'm leaning towards option A) Communications bull's eye. The image looks like a communication tool to me, and that fits the context of the question.
upvoted 0 times
...
Denise
17 days ago
This is a tricky one, but I'd have to say option B) Performance goals. The risk matrix seems to be focused on the project's performance targets.
upvoted 0 times
...
Stephanie
21 days ago
Hmm, the question is asking about the characteristics of the identified risks, and the image shows a risk matrix. I think option C) Earned value management goals is the best fit here.
upvoted 0 times
...
Timothy
23 days ago
This definitely looks like a project risk management question. The image shows a risk matrix, so I'm going to go with option D) Project exception report.
upvoted 0 times
...
Reena
1 months ago
We should focus on monitoring and controlling the project to ensure we meet those goals.
upvoted 0 times
...
Dylan
2 months ago
I agree, if we don't meet the performance goals, it could impact the project's success.
upvoted 0 times
...
Reena
2 months ago
I think the key risk here is not meeting the performance goals.
upvoted 0 times
...

Save Cancel