Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 3 Question 58 Discussion

Posted by Kattie on Sep 17, 2022 at 05:04 PM

Which of the following allows activities to be done in parallel that would normally be done in

equence?

Suggested Answer: C

Fast tracking is a technique for compressing project schedule. In fast tracking, phases

are overlapped that would normally be done in

sequence. It is shortening the project schedule without reducing the project scope.

Answer option D is incorrect. Crashing is a process in that the project manager adds more resources

to effort-driven activities in an attempt to

shorten their duration.

Answer option A is incorrect. A lag time is a delay between the predecessor and the successor tasks.

Sometimes it may be needed to

schedule a delay between the predecessor and the successor tasks. For example, if two coats of

paint are required to paint a car, then the

final coat should be applied only when the first coat dries. This delay is known as the lag time. The

lag time is entered as a positive value. The

lag time can be entered as a duration or as a percentage of the predecessor's task duration. It is

entered on the Predecessor tab in the Task

Information dialog box.

Answer option B is incorrect. A lead time is the time that overlaps between the predecessor and the

successor tasks. The successor task can

start before the predecessor task finishes. For example, if a task can start when its predecessor is

one-fourth finished, a finish-to-start

dependency with a lead time of 25 percent for the successor task can be specified. The lead time is

entered as a negative value. The lead time

can be entered as a duration or as a percentage of the predecessor's task duration. It is entered on

the Predecessor tab in the Task

Information dialog box.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
11 comments · newest first
AS
Ashlyn 12 months ago
Lag time just delays things, not really parallel work.
EL
Elliott 1 year ago
Totally agree, fast tracking is super effective!
AN
Antonio 1 year ago
Wait, can you really do activities in parallel like that?
PO
Portia 1 year ago
I thought crashing was for speeding things up?
LI
Lindsey 1 year ago
Fast tracking is the way to go!
WH
Whitley 1 year ago
Lag time sounds familiar, but I don't think it fits this question. Fast tracking seems to be the best choice based on what I studied.
AV
Avery 1 year ago
I practiced a question like this, and I feel like crashing is more about reducing time, not really about doing things in parallel.
MA
Malcolm 1 year ago
I'm not entirely sure, but I remember something about lead time being related to scheduling. Could it be that?
GE
Gearldine 1 year ago
I think fast tracking is the right answer because it involves overlapping tasks that usually happen one after the other.
AL
Alline 1 year ago
This seems like a straightforward question about the definition of the mean. I'll review my notes on measures of central tendency to make sure I have the right understanding.
LA
Lashawnda 1 year ago
I'm pretty sure PIM is a multicast routing protocol, so the answer has to be related to that. Let me think through the options...
0/2000 characters

Save Cancel