New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 3 Question 40 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 40
Topic #: 3
[All PMI-SP Questions]

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: Measurements Values BCWP (or EV)425 BCWS (or PV) 400 ACWP (or AC)510 What is the schedule performance index (SPI) of the project at the current point of time?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to the question, you are required to calculate the schedule performance

index (SPI) of the project. Schedule performance index

(SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future

performance. SPI is the ratio of earned

value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The SPI value of 1 indicates that the project is right on target. Here, SPI is calculated as

follows:

SPI = EV / PV

= 425/400

= 1.0625

As the SPI (1.0625) is greater than 1, it shows that the schedule performance is better than

expected.

What is BCWP (or EV)?

Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is

the budgeted amount

for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?

Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned

to the scheduled work

to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?

Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and

recorded in accomplishing

work performed during a given time period for a schedule activity. It is the cost of the work to date,

including direct and

indirect costs. AC is money that has actually been expended to date.


Contribute your Thoughts:

0/2000 characters
Nakisha
4 months ago
I thought SPI should always be above 1, this is surprising!
upvoted 0 times
...
Britt
4 months ago
Totally agree, it’s definitely option C!
upvoted 0 times
...
Carey
4 months ago
Wait, is that really the right calculation?
upvoted 0 times
...
Ashanti
4 months ago
That gives us 1.0625, right?
upvoted 0 times
...
Aliza
4 months ago
SPI is calculated as BCWP/BCWS, so it's 425/400.
upvoted 0 times
...
Franchesca
5 months ago
I keep mixing up BCWP and BCWS. Is BCWP the same as EV? I really need to double-check that.
upvoted 0 times
...
Chaya
5 months ago
If I recall correctly, the SPI should be around 1.06 based on the numbers given. I hope I calculated it right!
upvoted 0 times
...
Jules
5 months ago
I think I practiced a similar question where the SPI was less than 1, indicating a delay. I wonder if that applies here too.
upvoted 0 times
...
Tish
5 months ago
I remember the formula for SPI is EV divided by PV, but I'm not entirely sure about the values.
upvoted 0 times
...
Tamekia
5 months ago
This is a good question to test our understanding of quality awards and benchmarking. I feel confident I can reason through the right answer.
upvoted 0 times
...
Celeste
5 months ago
This is a tricky one. I need to make sure I understand the question correctly before selecting an answer. Let me think through the key areas of risk assessment that organizations should focus on.
upvoted 0 times
...
Peter
5 months ago
I feel pretty confident about this one. In an agile context, the team's feedback is crucial for refining the backlog, so I'm going to select "Team feedback" as the answer.
upvoted 0 times
...
Chana
5 months ago
Hmm, I'm a bit unsure here. I think A, B, and F might be the best options, as the salary range is also important information to include.
upvoted 0 times
...
Jennie
5 months ago
I remember we discussed the V model and how its structure might create risks if the testing phase takes too long. That could impact quality.
upvoted 0 times
...

Save Cancel