Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 25 Discussion

Actual exam question for PMI's PMI Scheduling Professional exam
Question #: 25
Topic #: 3
[All PMI Scheduling Professional Questions]

Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-

point estimate for his project. His project team, however, is complaining about participating in this

estimate type because of the time it takes to predict the duration of activities. Andy, as the project

manager, tells the project team that they must create the time estimate, as it will help this project

and future similar projects. What is a three-point estimate?

Show Suggested Answer Hide Answer
Suggested Answer: B

A three-point estimate requires that each activity be estimated for its optimistic, most

likely, and pessimistic duration. Once the three

estimates have been created, an average of the duration estimates is found and this is the recorded

duration for the project work.

Answer option A is incorrect. This is not a complete explanation of a three-point estimate.

Answer option C is incorrect. This is a definition of PERT, a similar time estimating technique.

Answer option D is incorrect. This is definition of PERT, but this answer uses the term GERT so it is

not a valid choice.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel