New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 2 Question 74 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 74
Topic #: 2
[All PMI-SP Questions]

You are the project manager for your company. You are working with the activities defined in the figure below.

What will happen to your project if Activity F takes five additional days to complete than what was expected?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

0/2000 characters
Alaine
3 months ago
Shifting to ACFI makes sense if F is delayed.
upvoted 0 times
...
Sherell
3 months ago
Totally agree, it’ll push us back by five days for sure!
upvoted 0 times
...
Paz
3 months ago
Wait, how can we still be on time if F is delayed? Sounds off.
upvoted 0 times
...
Vince
4 months ago
I think the float on Activity I could save us, though.
upvoted 0 times
...
Vincenza
4 months ago
If Activity F takes five extra days, the project will definitely be late.
upvoted 0 times
...
Maryann
4 months ago
I’m leaning towards the idea that we might end up with two critical paths if F is delayed, but I need to double-check that concept.
upvoted 0 times
...
Winifred
4 months ago
I feel like there's a chance we could still finish on time because of the float on Activity I, but I can't recall the specifics.
upvoted 0 times
...
Amber
4 months ago
I remember a practice question where we discussed critical paths, and I think if F is delayed, it could change the critical path.
upvoted 0 times
...
Jacqueline
5 months ago
I think if Activity F takes longer, it might push the whole project back, but I'm not sure if it's exactly five days late.
upvoted 0 times
...
Merilyn
5 months ago
This seems straightforward. If Activity F is on the critical path, a 5-day delay will push out the project end date by 5 days. I'll select that option.
upvoted 0 times
...
Argelia
5 months ago
I'm a little confused by the question. I'll need to walk through the activity network and calculate the new project duration to determine the correct answer.
upvoted 0 times
...
Rene
5 months ago
Okay, I think I've got this. If Activity F takes 5 more days, it will push out the critical path. I'll need to double-check the options to see which one best matches that scenario.
upvoted 0 times
...
Lucina
5 months ago
Hmm, I'm a bit unsure about this one. I'll need to review the activity network and calculate the new critical path to see how it changes.
upvoted 0 times
...
Jade
5 months ago
This looks like a classic critical path analysis problem. I'll need to carefully examine the activity dependencies and float to determine the impact.
upvoted 0 times
...
Evangelina
5 months ago
Hmm, I'm not sure about this one. The DRS threshold or the resync throttling could also be factors, but I'm not totally sure how those would impact the backend IOPs. I'll need to think this through carefully.
upvoted 0 times
...
Bok
5 months ago
This seems like a straightforward question about evaluating the effectiveness of requirements reviews. I think the key metrics we need are the number of defects found during the requirements review and the total number of defects attributable to requirements that were found throughout the testing process.
upvoted 0 times
...
Laquita
10 months ago
Ah, the joys of project management. It's like a game of Tetris, but with deadlines instead of blocks. I'll go with B and hope the client doesn't throw a fit.
upvoted 0 times
...
Dominga
10 months ago
Two critical paths? That's like having two left feet - it's just not going to work. D is definitely not the way to go here.
upvoted 0 times
Mendy
8 months ago
C) Your project can still complete on time as float is available on Activity I.
upvoted 0 times
...
Kimberely
8 months ago
B) Your project will be late by five days.
upvoted 0 times
...
Ammie
8 months ago
A) Your project's critical path will shift to ACFI.
upvoted 0 times
...
...
Weldon
10 months ago
I don't know about you guys, but I'm feeling a bit float-y after looking at this question. All joking aside, I think C is the correct answer here.
upvoted 0 times
Walker
8 months ago
That's a good point, so maybe C is the correct answer after all.
upvoted 0 times
...
Hortencia
9 months ago
But if there is float available on Activity I, then the project can still complete on time.
upvoted 0 times
...
Tess
9 months ago
I think it might actually be D, since Activity F is on the critical path.
upvoted 0 times
...
Thad
10 months ago
I agree, C seems like the best option.
upvoted 0 times
...
...
Anisha
10 months ago
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
upvoted 0 times
Bettina
9 months ago
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
upvoted 0 times
...
Jenelle
10 months ago
A) Your project's critical path will shift to ACFI.
upvoted 0 times
...
...
Cassie
11 months ago
Looks like Activity F is the culprit here. Shifting the critical path to ACFI seems like the obvious choice, but I wonder if the float on Activity I can really save the day.
upvoted 0 times
Kanisha
9 months ago
So, it's better to plan for the worst-case scenario and adjust accordingly.
upvoted 0 times
...
Narcisa
9 months ago
I'm not sure, but if Activity F takes five additional days, the project will be late by five days.
upvoted 0 times
...
Avery
9 months ago
But what if the float on Activity I can actually save the day?
upvoted 0 times
...
Belen
9 months ago
I think shifting the critical path to ACFI is the best option.
upvoted 0 times
...
...
Marti
11 months ago
But won't the critical path shift to ACFI if Activity F is delayed?
upvoted 0 times
...
Mirta
11 months ago
I disagree, I believe our project can still complete on time as float is available on Activity I.
upvoted 0 times
...
Marti
11 months ago
I think if Activity F takes five additional days, our project will be late by five days.
upvoted 0 times
...

Save Cancel