Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 2 Question 74 Discussion

Posted by Kimbery on Apr 13, 2024 at 01:59 AM

You are the project manager for your company. You are working with the activities defined in the figure below.

What will happen to your project if Activity F takes five additional days to complete than what was expected?

Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
37 comments · newest first
AL
Alaine 11 months ago
Shifting to ACFI makes sense if F is delayed.
SH
Sherell 11 months ago
Totally agree, it’ll push us back by five days for sure!
PA
Paz 12 months ago
Wait, how can we still be on time if F is delayed? Sounds off.
VI
Vince 12 months ago
I think the float on Activity I could save us, though.
VI
Vincenza 1 year ago
If Activity F takes five extra days, the project will definitely be late.
MA
Maryann 1 year ago
I’m leaning towards the idea that we might end up with two critical paths if F is delayed, but I need to double-check that concept.
WI
Winifred 1 year ago
I feel like there's a chance we could still finish on time because of the float on Activity I, but I can't recall the specifics.
AM
Amber 1 year ago
I remember a practice question where we discussed critical paths, and I think if F is delayed, it could change the critical path.
JA
Jacqueline 1 year ago
I think if Activity F takes longer, it might push the whole project back, but I'm not sure if it's exactly five days late.
ME
Merilyn 1 year ago
This seems straightforward. If Activity F is on the critical path, a 5-day delay will push out the project end date by 5 days. I'll select that option.
AR
Argelia 1 year ago
I'm a little confused by the question. I'll need to walk through the activity network and calculate the new project duration to determine the correct answer.
RE
Rene 1 year ago
Okay, I think I've got this. If Activity F takes 5 more days, it will push out the critical path. I'll need to double-check the options to see which one best matches that scenario.
LU
Lucina 1 year ago
Hmm, I'm a bit unsure about this one. I'll need to review the activity network and calculate the new critical path to see how it changes.
JA
Jade 1 year ago
This looks like a classic critical path analysis problem. I'll need to carefully examine the activity dependencies and float to determine the impact.
EV
Evangelina 1 year ago
Hmm, I'm not sure about this one. The DRS threshold or the resync throttling could also be factors, but I'm not totally sure how those would impact the backend IOPs. I'll need to think this through carefully.
BO
Bok 1 year ago
This seems like a straightforward question about evaluating the effectiveness of requirements reviews. I think the key metrics we need are the number of defects found during the requirements review and the total number of defects attributable to requirements that were found throughout the testing process.
LA
Laquita 1 year ago
Ah, the joys of project management. It's like a game of Tetris, but with deadlines instead of blocks. I'll go with B and hope the client doesn't throw a fit.
DO
Dominga 2 years ago
Two critical paths? That's like having two left feet - it's just not going to work. D is definitely not the way to go here.
ME
Mendy 1 year ago
↳ replying to Dominga
C) Your project can still complete on time as float is available on Activity I.
KI
Kimberely 1 year ago
↳ replying to Dominga
B) Your project will be late by five days.
AM
Ammie 1 year ago
↳ replying to Dominga
A) Your project's critical path will shift to ACFI.
WE
Weldon 2 years ago
I don't know about you guys, but I'm feeling a bit float-y after looking at this question. All joking aside, I think C is the correct answer here.
WA
Walker 1 year ago
↳ replying to Weldon
That's a good point, so maybe C is the correct answer after all.
HO
Hortencia 1 year ago
↳ replying to Weldon
But if there is float available on Activity I, then the project can still complete on time.
TE
Tess 1 year ago
↳ replying to Weldon
I think it might actually be D, since Activity F is on the critical path.
TH
Thad 2 years ago
↳ replying to Weldon
I agree, C seems like the best option.
AN
Anisha 2 years ago
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
BE
Bettina 1 year ago
↳ replying to Anisha
Five extra days for Activity F? That's going to put a serious dent in the project's timeline. B is the way to go, no doubt about it.
JE
Jenelle 2 years ago
↳ replying to Anisha
A) Your project's critical path will shift to ACFI.
CA
Cassie 2 years ago
Looks like Activity F is the culprit here. Shifting the critical path to ACFI seems like the obvious choice, but I wonder if the float on Activity I can really save the day.
KA
Kanisha 1 year ago
↳ replying to Cassie
So, it's better to plan for the worst-case scenario and adjust accordingly.
NA
Narcisa 1 year ago
↳ replying to Cassie
I'm not sure, but if Activity F takes five additional days, the project will be late by five days.
AV
Avery 1 year ago
↳ replying to Cassie
But what if the float on Activity I can actually save the day?
BE
Belen 1 year ago
↳ replying to Cassie
I think shifting the critical path to ACFI is the best option.
MA
Marti 2 years ago
But won't the critical path shift to ACFI if Activity F is delayed?
MI
Mirta 2 years ago
I disagree, I believe our project can still complete on time as float is available on Activity I.
MA
Marti 2 years ago
I think if Activity F takes five additional days, our project will be late by five days.
0/2000 characters

Save Cancel