Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 2 Question 46 Discussion

Posted by Harrison on May 08, 2022 at 09:32 AM

You are the project manager for the NGH project. The figure given below represents the small

project you are completing for your organization.

How much float can you use on Activity G if Activity B actually takes eight days to complete?

Suggested Answer: D

If Activity B uses seven days of float, which it can, it does not allow Activity D, G, or J to

have any float available. This is because the total

duration of path ABDGJK cannot exceed 30 days, the duration of the project. If Activity B uses the

seven days of float, then the path meets

the project's duration at Day 30.

Answer options B and A are incorrect. These are not the valid calculation.

Answer option C is incorrect. Seven represents the amount of float available on Activity G before

Activity B uses the available float.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
14 comments · newest first
CH
Chara 1 year ago
Totally agree, 4 days makes sense!
RE
Reid 1 year ago
Wait, how can it be 4? I’m not so sure about that.
JO
Josefa 1 year ago
Definitely 4 days, that’s the calculation!
FR
Franklyn 1 year ago
I think it should be 3 days, though.
DA
Darrin 1 year ago
Float for Activity G is 4 days if B takes 8 days.
GA
Gary 1 year ago
I’m a bit confused about how to calculate the float here. I thought float was just based on total project duration, but now I’m not so sure.
CE
Celia 1 year ago
I feel like I might have seen a question where we had to adjust float based on changes in activity durations. I think the answer could be zero if G is on the critical path.
DA
Dalene 1 year ago
This question seems similar to the practice problems we did last week. I think if Activity B takes longer, it might reduce the float for G, but I can't recall the exact numbers.
CI
Ciara 1 year ago
I remember we discussed float calculations in class, but I'm not entirely sure how Activity B's duration affects Activity G's float.
PA
Paola 1 year ago
The firewall blocking the port is the most obvious reason, in my opinion. I'll make sure to select that one.
FI
Filiberto 1 year ago
Hmm, I'm a bit confused here. The question is asking about IEEE standards, but the answer choices seem to be about other wireless technologies like WiMAX and Bluetooth. I'll need to carefully read the statement and think about which standard the IEEE 802.11 series actually refers to.
MA
Marleen 1 year ago
Hmm, I'm not entirely sure about this one. The options seem to be talking about different Splunk commands and features, but I'm not sure which one is the best way to test for a normalized data model.
LA
Lashaunda 1 year ago
I'm confident I know the right answer here. The principles of testing are well-covered in the course material, so I should be able to identify the correct ones.
YO
Youlanda 1 year ago
I have a hunch that options C and D are incorrect because they assume the data is in a list format. But I'm still debating between A and B.
0/2000 characters

Save Cancel