New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 2 Question 34 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 34
Topic #: 2
[All PMI-SP Questions]

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

0/2000 characters
Devorah
4 months ago
Five seems way too high for this activity.
upvoted 0 times
...
Vanesa
4 months ago
I calculated it as three, not zero!
upvoted 0 times
...
Glendora
4 months ago
Wait, are we sure about that? Seems off to me.
upvoted 0 times
...
My
4 months ago
Definitely agree, zero makes sense here.
upvoted 0 times
...
Mignon
4 months ago
I think the total float for Activity I is zero.
upvoted 0 times
...
Bernardo
5 months ago
I feel like the answer could be three, but I need to double-check the dependencies in the diagram to be sure.
upvoted 0 times
...
Delbert
5 months ago
I practiced a question like this where the total float was five, but I can't recall if it applies here.
upvoted 0 times
...
Valene
5 months ago
I think total float for Activity I might be zero, but I could be mixing it up with another activity from our study materials.
upvoted 0 times
...
Ethan
5 months ago
I remember calculating total float in similar practice questions, but I'm not sure about the exact values for this diagram.
upvoted 0 times
...
Brynn
5 months ago
Hmm, this looks like a tricky one. I'll need to carefully examine the event metadata and the DROP USER command to determine the effect on the event.
upvoted 0 times
...
Lore
5 months ago
This seems straightforward - I think I'd go with option B and just change the access levels in the marketing user standard profile.
upvoted 0 times
...
Elden
5 months ago
TFTP and FTP seem less secure options, but I might be mixing up ACI protocols with something else.
upvoted 0 times
...

Save Cancel