Examine the figure given below.

In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Devorah
10 months agoVanesa
11 months agoGlendora
11 months agoMy
11 months agoMignon
11 months agoBernardo
11 months agoDelbert
11 months agoValene
11 months agoEthan
11 months agoBrynn
12 months agoLore
12 months agoElden
12 months ago