New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 72 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 72
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

0/2000 characters
Linn
3 months ago
Totally agree, that sounds about right!
upvoted 0 times
...
Elise
3 months ago
Wait, how can we be only 60% done but have spent so much?
upvoted 0 times
...
Dorthy
3 months ago
I think it’s around -$111,750, right?
upvoted 0 times
...
Sang
4 months ago
Cost variance is definitely negative here.
upvoted 0 times
...
Lindsey
4 months ago
The BAC is $745,000 and we've spent $440,000 so far.
upvoted 0 times
...
Odelia
4 months ago
I feel like I should just plug in the numbers, but I keep mixing up the terms. Is it possible that the variance could be zero if we're behind schedule?
upvoted 0 times
...
Diane
4 months ago
I practiced a similar question where we had to find the cost variance, and I think the answer was negative, indicating we're over budget.
upvoted 0 times
...
Lawana
4 months ago
I remember something about the formula being CV = EV - AC, but I can't recall how to calculate EV with the BAC and percentage complete.
upvoted 0 times
...
Kattie
5 months ago
I think the cost variance is calculated by subtracting the actual cost from the earned value, but I'm not entirely sure how to find the earned value here.
upvoted 0 times
...
Paulene
5 months ago
Alright, time to put my project management skills to the test. I'll start by calculating the Earned Value, then subtract the Actual Cost to find the Cost Variance. Gotta show my work to get full credit on this one.
upvoted 0 times
...
Jerrod
5 months ago
I've got this! The key is to use the formula: Cost Variance = Earned Value - Actual Cost. With the given BAC, actual cost, and percent complete, I can plug those numbers in and solve for the cost variance.
upvoted 0 times
...
Casandra
5 months ago
I'm a bit confused on how to approach this. Can someone walk me through the formula for calculating cost variance? I want to make sure I have the right approach before diving in.
upvoted 0 times
...
Major
5 months ago
Okay, let me think this through step-by-step. I need to find the expected cost at the third milestone and compare it to the actual cost spent so far to determine the cost variance.
upvoted 0 times
...
Vicente
5 months ago
Hmm, this looks like a tricky one. I'll need to carefully calculate the cost variance based on the given information about the project's budget, spending, and completion status.
upvoted 0 times
...
Christiane
5 months ago
I think the key steps here are to use the pack and unpack tools to transfer the domain configuration to the new machine. The Configuration Wizard could also be useful for cloning the domain.
upvoted 0 times
...
Taryn
5 months ago
I'm pretty confident on this one. The Extract process is the one that writes to the trail files, so it makes sense that it would be the one to include the PURGEOLDEXTRACTS parameter to clean them up. The Replicat process just reads from the trail files, so it wouldn't be responsible for managing them.
upvoted 0 times
...
Mozell
9 months ago
Wait, so the project is only 60% complete but they've already spent over 50% of the budget? This project manager must be cooking the books or something. I'm going with B) $-111,750 and hoping they get fired.
upvoted 0 times
...
Francene
10 months ago
I'm going with D) $7,000. I know it's not the most obvious answer, but maybe the project manager is a wizard and has somehow managed to keep the costs in check despite the schedule slip. I'm feeling lucky with this one!
upvoted 0 times
Ailene
8 months ago
D) $7,000
upvoted 0 times
...
Launa
9 months ago
B) $-111,750
upvoted 0 times
...
Detra
9 months ago
A) 11,667
upvoted 0 times
...
...
Matthew
10 months ago
Haha, 'no variance'? That's a good one! With this much of a budget and schedule slip, I'd be surprised if there wasn't a significant cost variance. B) $-111,750 is my pick.
upvoted 0 times
Fletcher
9 months ago
Let's hope we can get back on track and improve our cost performance in the next milestone.
upvoted 0 times
...
Dana
9 months ago
Yeah, it's definitely not a 'no variance' situation with the budget and schedule slip we're facing.
upvoted 0 times
...
Tamar
9 months ago
I agree, B) $-111,750 seems like the most likely cost variance given the situation.
upvoted 0 times
...
...
Kristine
10 months ago
C) There is no variance? Are you kidding me? With a 60% completion and $440,000 spent out of a $745,000 budget, there's clearly a cost variance. I'm going with B.
upvoted 0 times
Lakeesha
9 months ago
Yeah, definitely not C. B makes the most sense with the information given.
upvoted 0 times
...
Paz
9 months ago
I think you're right, B seems like the correct answer.
upvoted 0 times
...
...
Ronald
10 months ago
I believe the correct answer is B) $-111,750 because the formula for cost variance is EV - AC, and in this case, it is $745,000 - $440,000.
upvoted 0 times
...
Alesia
11 months ago
I agree with Lawrence. The cost variance is negative because we are over budget.
upvoted 0 times
...
Dalene
11 months ago
I think the answer is B) $-111,750. The cost variance is the difference between the budgeted cost and the actual cost, and with the given information, that's the correct answer.
upvoted 0 times
Leoma
9 months ago
D) $7,000
upvoted 0 times
...
Weldon
9 months ago
C) There is no variance.
upvoted 0 times
...
Marti
9 months ago
B) $-111,750
upvoted 0 times
...
Elbert
10 months ago
A) 11,667
upvoted 0 times
...
...
Lawrence
11 months ago
I think the answer is B) $-111,750.
upvoted 0 times
...

Save Cancel