You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Linn
10 months agoElise
10 months agoDorthy
10 months agoSang
10 months agoLindsey
11 months agoOdelia
11 months agoDiane
11 months agoLawana
11 months agoKattie
11 months agoPaulene
11 months agoJerrod
11 months agoCasandra
11 months agoMajor
11 months agoVicente
11 months agoChristiane
12 months agoTaryn
12 months agoMozell
1 year agoFrancene
1 year agoAilene
1 year agoLauna
1 year agoDetra
1 year agoMatthew
1 year agoFletcher
1 year agoDana
1 year agoTamar
1 year agoKristine
1 year agoLakeesha
1 year agoPaz
1 year agoRonald
1 year agoAlesia
1 year agoDalene
1 year agoLeoma
1 year agoWeldon
1 year agoMarti
1 year agoElbert
1 year agoLawrence
1 year ago