You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Linn
5 months agoElise
5 months agoDorthy
5 months agoSang
5 months agoLindsey
6 months agoOdelia
6 months agoDiane
6 months agoLawana
6 months agoKattie
6 months agoPaulene
6 months agoJerrod
6 months agoCasandra
6 months agoMajor
6 months agoVicente
6 months agoChristiane
7 months agoTaryn
7 months agoMozell
11 months agoFrancene
11 months agoAilene
10 months agoLauna
10 months agoDetra
11 months agoMatthew
12 months agoFletcher
10 months agoDana
10 months agoTamar
11 months agoKristine
1 year agoLakeesha
11 months agoPaz
11 months agoRonald
1 year agoAlesia
1 year agoDalene
1 year agoLeoma
11 months agoWeldon
11 months agoMarti
11 months agoElbert
11 months agoLawrence
1 year ago