Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 1 Question 72 Discussion

Actual exam question for PMI's PMI Scheduling Professional exam
Question #: 72
Topic #: 1
[All PMI Scheduling Professional Questions]

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Louisa
12 days ago
Haha, yeah, it does kind of look like a Jackson Pollock painting. Maybe they're testing our ability to analyze abstract project plans.
upvoted 0 times
...
Herminia
14 days ago
Hmm, I'm not so sure about that. Let me double-check the calculations. Wait, I think you're right! B) Zero is the correct answer.
upvoted 0 times
Chauncey
11 hours ago
Let's calculate it again.
upvoted 0 times
...
...
Lindsey
15 days ago
Hey, has anyone else noticed that the diagram looks a bit like a modern art piece? I wonder if the exam designers are trying to throw us off.
upvoted 0 times
...
Nikita
16 days ago
Okay, I think I've got it. Based on the information in the diagram, the total float for Activity I is... B) Zero.
upvoted 0 times
...

Save Cancel