Which of the following is NOT an output of the control schedule process?
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
Kenda
10 months agoAzalee
10 months agoRonny
10 months agoMalcolm
10 months agoDonette
11 months agoCyril
11 months agoElouise
11 months agoMignon
11 months agoBobbye
11 months agoYolando
11 months agoAliza
11 months agoToi
11 months agoKirby
11 months agoElina
12 months agoPenney
12 months agoAntonette
12 months agoVon
2 years agoBernadine
2 years agoChuck
2 years agoVeta
2 years agoBeth
2 years agoJonell
2 years agoRasheeda
2 years agoKerry
2 years agoSharen
2 years agoElbert
2 years ago