New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 67 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 67
Topic #: 1
[All PMI-SP Questions]

Which of the following is NOT an output of the control schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: C

The project termination request is not an output of the control schedule. Early

termination of a project is a closing process and usually does

not stem from the project manager.

The outputs of the control schedule process are as follows:

Work Performance Measurements: The work packages and control accounts are documented and

communicated to the stakeholders.

Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen

and the reasons, causes of

variance, and other types of lessons learned from project schedule control.

Change Requests: It is processed for reviews and disposition through the Perform Integrated Change

Control process.

Project Management Plan Updates: The elements that need to be updated are: schedule baseline,

schedule management plan, cost

baseline.

Project Document Updates: The elements that need to be updated in project document updates are:

schedule data and project

schedule.


Contribute your Thoughts:

0/2000 characters
Kenda
3 months ago
Really? I didn't know project termination requests weren't outputs!
upvoted 0 times
...
Azalee
3 months ago
I agree with Jane, C seems off.
upvoted 0 times
...
Ronny
3 months ago
Wait, are you sure about that? I thought change requests were included.
upvoted 0 times
...
Malcolm
4 months ago
I think it's C, project termination requests aren't part of that.
upvoted 0 times
...
Donette
4 months ago
Definitely not A, that's a common output.
upvoted 0 times
...
Cyril
4 months ago
I'm a bit confused; I thought all of these could be outputs in some context, but I guess only some are specific to the control schedule.
upvoted 0 times
...
Elouise
4 months ago
I feel like I've seen a question like this before, and I think project termination requests aren't typically outputs of the control schedule process.
upvoted 0 times
...
Mignon
4 months ago
I remember studying that organizational process assets are definitely an output, but I can't recall if project document updates are included.
upvoted 0 times
...
Bobbye
5 months ago
I think the control schedule process outputs change requests, but I'm not sure about the project termination request. That one seems a bit off.
upvoted 0 times
...
Yolando
5 months ago
I'm confident that the correct answer is A. Organizational process assets are an input to the control schedule process, not an output.
upvoted 0 times
...
Aliza
5 months ago
The key is to focus on the specific outputs of the control schedule process, not just general project management outputs. I think the answer is A.
upvoted 0 times
...
Toi
5 months ago
Hmm, I'm a bit confused on this one. I'll need to review the control schedule process to make sure I understand the outputs.
upvoted 0 times
...
Kirby
5 months ago
I'm pretty sure the answer is A. Organizational process assets are not an output of the control schedule process.
upvoted 0 times
...
Elina
5 months ago
Okay, I think I've got a good handle on this. The key is to focus on the cost and flexibility requirements for the 20-30 month migration timeline. I'm leaning towards one of the dark fiber options.
upvoted 0 times
...
Penney
5 months ago
I'm feeling pretty confident about this one. The key is to configure the right MED settings on the appropriate BGP processes to influence the route selection as needed.
upvoted 0 times
...
Antonette
5 months ago
I'm leaning towards option D. Gently reminding the person is a good first step, but if the violation persists, I have a responsibility to report it.
upvoted 0 times
...
Von
2 years ago
Hmm, good point, Bernadine. But I still think C is the correct answer. A project termination request is more closely tied to the close project or phase process, where you're actually wrapping up the whole project or a specific phase. The control schedule process is more about keeping things on track, not pulling the plug entirely.
upvoted 0 times
...
Bernadine
2 years ago
You know, I was thinking the same thing, but then I remembered that sometimes a project might need to be terminated during the execution phase. Wouldn't that create a project termination request as an output of the control schedule process? I'm not 100% sure, but it's worth considering.
upvoted 0 times
...
Chuck
2 years ago
I agree with Veta on this one. The control schedule process is all about monitoring and controlling the project schedule, so things like organizational process assets, change requests, and project document updates make sense as outputs. But a project termination request? That's a whole different ball game.
upvoted 0 times
...
Veta
2 years ago
Ah, the control schedule process - a real head-scratcher, isn't it? Let's see, I think the answer has to be C) Project termination request. That's more of an output of the close project or phase process, not the control schedule process.
upvoted 0 times
Beth
2 years ago
Thanks for clarifying that!
upvoted 0 times
...
Jonell
2 years ago
Exactly, that's the correct answer.
upvoted 0 times
...
Rasheeda
2 years ago
That makes sense. So, the answer would be C) Project termination request.
upvoted 0 times
...
Kerry
2 years ago
I believe Organizational process assets, Change requests, and Project document updates are all outputs of the control schedule process.
upvoted 0 times
...
Sharen
2 years ago
So what do you think would be a correct output of the control schedule process?
upvoted 0 times
...
Elbert
2 years ago
I think you're right, Project termination request is not an output of the control schedule process.
upvoted 0 times
...
...

Save Cancel