New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 39 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 39
Topic #: 1
[All PMI-SP Questions]

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Show Suggested Answer Hide Answer
Suggested Answer: B

Fred should add lag time to each painting activity. Since lag time is waiting time, Fred

will have to wait twenty-four hours after the priming is

finished before he can start painting.

What is a lag?

A lag directs a delay in the successor activity. Lags require the dependent activity to have added

either to the start date or

to the finish date of the activity. For example, in a project of making radio-controlled airplanes, after

applying glue and

pasting stickers, it requires twenty-four hours to dry the glue. Any activity can be started after that

only. This period, of

twenty-four hours, is a lag.

Answer option C is incorrect. There is no reason to add an intermediary task as waiting. Adding lag

time is the most appropriate as there are

fewer activities to manage.

Answer option D is incorrect. Priming all of the room first and then painting all of the rooms would

cause Fred to readjust the entire

sequencing of activities. In addition, we do not know the reason why Fred has scheduled all the

rooms to be primed and then painted. There

may be successor activities in the project that need to enter each room, such as carpeting, as soon

as a room has been painted. If that were

the case the additional activities would have to wait for all of the priming to be completed and then

the sequential rooms to be painted before

they could start.

Answer option A is incorrect. Lead time actually moves activities closer together rather than farther

apart. Lead time would cause the painting

and priming activities to overlap, something that Fred does not want to happen.

What is a lead?

A lead allows an acceleration of the successor activity. It works just the opposite of lag. For example,

in a software

application project, before designing is fully completed for first phase, a program development

group can start this phase

programming. This overlapping of timing is a lead.


Contribute your Thoughts:

0/2000 characters
Shannon
4 months ago
Wait, can they really paint all 456 rooms in a row? Seems risky!
upvoted 0 times
...
Krissy
4 months ago
Scheduling all rooms to be primed first is smart!
upvoted 0 times
...
Bettyann
4 months ago
An intermediary task sounds like overkill.
upvoted 0 times
...
Son
4 months ago
I think lag time is the way to go.
upvoted 0 times
...
Gail
4 months ago
Adding 24 hours of lead time makes sense!
upvoted 0 times
...
Kiera
5 months ago
I feel like scheduling all the priming first makes sense, but I’m not sure if that’s the best approach. It seems like it could lead to delays if something goes wrong.
upvoted 0 times
...
Jerry
5 months ago
I practiced a similar question where we had to account for curing times. I think adding an intermediary task could be a good way to handle this, but I’m not entirely confident.
upvoted 0 times
...
Elden
5 months ago
I remember something about lead time and lag time, but I'm not sure which one applies here. I think lead time might be for starting tasks earlier, but I could be wrong.
upvoted 0 times
...
Alona
5 months ago
I think lag time is what Fred needs to use here since it’s about waiting for the primer to cure before starting the painting. But I could see how some might confuse it with lead time.
upvoted 0 times
...
Kindra
5 months ago
Hmm, I'm leaning towards the automation execution threads being the right answer here. The "ExecutionLink From:" lines seem to be related to the execution of the automation, so that's my best guess.
upvoted 0 times
...
Dorothy
5 months ago
Okay, let's see here. The question is asking about what needs to be removed before installing the RTN 300. I'm pretty confident the answer is B - the protective cover on the antenna port.
upvoted 0 times
...
Lezlie
5 months ago
The key here is understanding the components of the full-memory desktop solution. If I can remember what each disk type is used for, I should be able to select the correct answer.
upvoted 0 times
...
Denny
5 months ago
I'm not sure about this one. The options all sound pretty technical and specific to Huawei's products. I'll need to make an educated guess, but I'm not feeling super confident about it.
upvoted 0 times
...

Save Cancel