New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 36 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 36
Topic #: 1
[All PMI-SP Questions]

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is

currently 40 percent complete, though it

was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management

would like to know if there is a schedule

variance. What is the planned value for this project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The planned value is the percentage of where the project should be times the budget at

completion. In this instance, it is 45 percent of the

$950,000. Here, it can be calculated as follows:

PV = 45% of BAC

= 0.45 * 950,000

= 427,500

Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a

schedule activity or work breakdown

structure component. It serves as a baseline against which actual performance is measured. The

theory of planned value is of vital importance

to the project management team and it is important to keep careful track of this. The term planned

value can also be in some situations

referred to by the project management team and the project management team leader as the

budgeted cost of work scheduled (BCWS).

Answer option A is incorrect. -$47,500 is the schedule variance (SV = EV-PV).

Answer option B is incorrect. This is the schedule performance index (SPI = EV/PV).

Answer option D is incorrect. This is the cost performance index (CPI = EV/AC).


Contribute your Thoughts:

0/2000 characters
Jamal
4 months ago
I thought it would be lower, interesting!
upvoted 0 times
...
Reuben
4 months ago
Yup, that’s right!
upvoted 0 times
...
Amina
4 months ago
Wait, how did you get that number?
upvoted 0 times
...
Janet
4 months ago
Totally agree, that makes sense!
upvoted 0 times
...
Alonzo
4 months ago
The planned value is $427,500.
upvoted 0 times
...
Sol
5 months ago
I thought the planned value was just the total budget divided by the percentage complete, but that doesn't seem right. I need to double-check how to calculate it properly.
upvoted 0 times
...
Dottie
5 months ago
I practiced a similar question where we had to find the planned value too. If I recall correctly, it should be $427,500 for this one since it's 45% of $950,000.
upvoted 0 times
...
Lashon
5 months ago
I'm a bit unsure about the exact formula, but I remember something about multiplying the BAC by the planned percentage. I hope I can remember the right numbers during the exam.
upvoted 0 times
...
Arminda
5 months ago
I think the planned value is calculated based on the budget at completion and the percentage of work scheduled. So, it should be something like 45% of $950,000, right?
upvoted 0 times
...
Rocco
5 months ago
Hmm, I'm not sure. Cloud backup seems like the right answer, but I want to double-check the other options just to be sure.
upvoted 0 times
...
Jenelle
5 months ago
This seems like a straightforward question about cost behavior. As revenue increases, variable costs tend to increase, consuming a higher percentage of revenue, so I'll go with option C.
upvoted 0 times
...
Lourdes
5 months ago
This question seems straightforward, but I want to make sure I understand the concepts correctly before answering.
upvoted 0 times
...
Louvenia
5 months ago
Okay, let me think this through. The ISR 1000 is a routing solution, so option A could be a good fit. But I'm not sure if it's just for customers who don't need SD-WAN.
upvoted 0 times
...

Save Cancel