Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 24 Discussion

Posted by Cristal on May 08, 2022 at 07:30 PM

You work as a Project Manager for Media Perfect Inc. Several projects are running under your

supervision. Rick, team leader of a project, provides you performance indexes of his project. The

schedule variance (SV) of his project is 25. What does this figure depict?

Suggested Answer: D

According to the question, the schedule variance (SV) of the project is 25, which is a

positive value. The positive SV depicts that the project is

ahead of the planned schedule.

What is SV?

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead

or behind what was planned for this period in time. The schedule variance is calculated based on the

following formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the

project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.

Answer option A is incorrect. The negative SV means that project is behind the schedule.

Answer option C is incorrect. The zero SV means that project is right on target.

Answer option B is incorrect. This result can be drawn by looking at the cost variance (CV) of the

project.

What is CV?

Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are

higher than budgeted

or lower than budgeted. The cost variance is calculated based on the following formula:

CV = Earned Value (EV) - Actual Cost (AC)

A positive value means that spending is less than budgeted, whereas a negative value indicates that

costs are higher than

originally planned for the project.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
AV
Avery 1 year ago
Nope, project is on target if SV is zero.
RO
Rosalyn 1 year ago
I thought SV meant you were behind, this is surprising!
LU
Luisa 1 year ago
Wait, isn't a high SV usually a red flag?
LO
Loise 1 year ago
Totally agree, that's a good sign!
CH
Chun 1 year ago
SV of 25 means the project is ahead of schedule!
HI
Hildred 1 year ago
I feel like I’ve seen this before. If SV is positive, it usually means the project is on track or ahead, right?
LO
Long 1 year ago
I’m a bit confused. Does a schedule variance of 25 really mean we’re ahead? I thought it could also relate to costs somehow.
BR
Brandon 1 year ago
I remember a practice question where a negative SV indicated being behind schedule. So, I guess a positive one like 25 means we're doing well?
JA
Janna 1 year ago
I think a positive SV means the project is ahead of schedule, but I'm not completely sure.
CA
Caprice 1 year ago
I'm a little confused on this one. I know DBCA is for database configuration, but I'm not sure if it can do things like change the standard block size or configure incremental backups. I'll have to review the DBCA functionality before the exam.
LI
Lindsey 1 year ago
This looks like a straightforward API request question. I'll carefully read through the options and think about which one best matches the criteria of searching for a process window containing the word 'secret'.
JU
Judy 1 year ago
Okay, I think I've got this. Configuring the virtual network address space should allow me to block internet access while still maintaining access to the necessary Microsoft services. I'll give it a try.
0/2000 characters

Save Cancel