New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 15 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 15
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Show Suggested Answer Hide Answer
Suggested Answer: B

Your schedule variance is -$33,750. You can find this by using the formula earned value-

minus planned.

Answer option C is incorrect. Cost is not the largest variance in the project.

Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).

Answer option D is incorrect. -$20,000 is the variance at completion for the project.


Contribute your Thoughts:

0/2000 characters
Willie
4 months ago
Totally agree, the schedule is the biggest issue!
upvoted 0 times
...
Kelvin
4 months ago
Wait, how did it get that far off schedule?
upvoted 0 times
...
Glory
4 months ago
I think the cost variance is more significant, $278,000!
upvoted 0 times
...
Cecily
4 months ago
Definitely a schedule variance here, -$33,750.
upvoted 0 times
...
Elouise
4 months ago
The BAC is $675,000 and you're at 40% completion.
upvoted 0 times
...
Arminda
5 months ago
I think the answer might be B, but I’m not entirely confident. The numbers seem tricky, especially with the budget spent already.
upvoted 0 times
...
Blondell
5 months ago
I feel like the cost variance is also important, but I can't recall if it's supposed to be negative or positive in this case.
upvoted 0 times
...
Luz
5 months ago
I think the schedule variance is more significant since we're behind on our completion percentage. I practiced a similar question where the schedule was the main issue.
upvoted 0 times
...
Layla
5 months ago
I remember we calculated variances in class, but I'm not sure how to apply it here. Is it just about the budget or the schedule too?
upvoted 0 times
...
Theresia
5 months ago
I'm a bit confused on the details of the Logic Centralization and Contract Centralization patterns. I'll need to review those before I can confidently answer this.
upvoted 0 times
...
Carmen
5 months ago
Sales Insights looks like the best option here. It's designed to help sales teams work together and share customer information.
upvoted 0 times
...
Corinne
5 months ago
Okay, I think I've got a handle on this. The key benefits of the Import DRM feature seem to be the ability to import hierarchies, preview data before merging, and automate the process. I'll make sure to highlight those points in my answer.
upvoted 0 times
...
Annabelle
5 months ago
Hmm, I'm a bit confused on this one. I know PolarDB is a cloud-based database service, but I'm not sure which specific engines it supports. I'll have to think this through carefully.
upvoted 0 times
...

Save Cancel