You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
Your schedule variance is -$33,750. You can find this by using the formula earned value-
minus planned.
Answer option C is incorrect. Cost is not the largest variance in the project.
Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).
Answer option D is incorrect. -$20,000 is the variance at completion for the project.
Willie
4 months agoKelvin
4 months agoGlory
4 months agoCecily
4 months agoElouise
4 months agoArminda
5 months agoBlondell
5 months agoLuz
5 months agoLayla
5 months agoTheresia
5 months agoCarmen
5 months agoCorinne
5 months agoAnnabelle
5 months ago