PMI-SP Exam - Topic 1 Question 14 Discussion

Posted by Estrella on May 07, 2022 at 11:39 AM

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Suggested Answer: A, C, D

The outputs to the determine budget process are as follows:

Cost performance baseline: The cost performance baseline is an authorized time-phased budget at

completion.

Project funding requirements: The project funding requirements are determined from total funding

requirements and periodic funding

requirements.

Project document updates: The project document updates consists of risk register, cost estimates

and project schedule.

Answer option B is incorrect. Scope baseline is an input to the determine budget process.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
13 comments · newest first
OM
Omer 1 year ago
Totally agree, all of these are key outputs!
DE
Derick 1 year ago
Wait, are project document updates really an output?
NI
Nieves 1 year ago
Scope baseline? Not sure about that one.
WI
Willetta 1 year ago
I think project funding requirements are also included.
IL
Iluminada 1 year ago
Definitely the cost performance baseline!
AR
Arlene 1 year ago
I feel like I saw a question like this before, and I'm pretty sure the cost performance baseline is one of the outputs, but I'm uncertain about the others.
MI
Michael 1 year ago
I practiced a similar question, and I believe the cost performance baseline and project funding requirements are correct, but I can't recall if project document updates are included.
AR
Aretha 1 year ago
I think the scope baseline is definitely part of the outputs, but I might be mixing it up with the project funding requirements.
GR
Grover 1 year ago
I remember that the Determine Budget process outputs include the cost performance baseline, but I'm not entirely sure about the project document updates.
PA
Patrick 1 year ago
Hmm, I'm a bit unsure about this one. I'll need to review my notes on the responsibilities of a P3O.
SA
Sage 1 year ago
This seems pretty straightforward. I'd focus on reviewing the contract details and interviewing the relevant parties to understand the billing issues.
KI
Kiley 1 year ago
I've seen questions like this before. The key is to pay attention to the details and understand the implications of the code. I'm feeling pretty confident about this one.
MI
Mirta 1 year ago
Business plans should be agile, that's the whole point. This has to be true.
0/2000 characters

Save Cancel