Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 1 Question 14 Discussion

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
A) Project document updates and C) Cost performance baseline and D) Project funding requirements
B) Scope baseline

PMI-SP Exam - Topic 1 Question 14 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 14
Topic #: 1
[All PMI-SP Questions]

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, C, D

The outputs to the determine budget process are as follows:

Cost performance baseline: The cost performance baseline is an authorized time-phased budget at

completion.

Project funding requirements: The project funding requirements are determined from total funding

requirements and periodic funding

requirements.

Project document updates: The project document updates consists of risk register, cost estimates

and project schedule.

Answer option B is incorrect. Scope baseline is an input to the determine budget process.


Contribute your Thoughts:

0/2000 characters
Omer
10 months ago
Totally agree, all of these are key outputs!
upvoted 0 times
...
Derick
11 months ago
Wait, are project document updates really an output?
upvoted 0 times
...
Nieves
11 months ago
Scope baseline? Not sure about that one.
upvoted 0 times
...
Willetta
11 months ago
I think project funding requirements are also included.
upvoted 0 times
...
Iluminada
11 months ago
Definitely the cost performance baseline!
upvoted 0 times
...
Arlene
11 months ago
I feel like I saw a question like this before, and I'm pretty sure the cost performance baseline is one of the outputs, but I'm uncertain about the others.
upvoted 0 times
...
Michael
11 months ago
I practiced a similar question, and I believe the cost performance baseline and project funding requirements are correct, but I can't recall if project document updates are included.
upvoted 0 times
...
Aretha
11 months ago
I think the scope baseline is definitely part of the outputs, but I might be mixing it up with the project funding requirements.
upvoted 0 times
...
Grover
11 months ago
I remember that the Determine Budget process outputs include the cost performance baseline, but I'm not entirely sure about the project document updates.
upvoted 0 times
...
Patrick
12 months ago
Hmm, I'm a bit unsure about this one. I'll need to review my notes on the responsibilities of a P3O.
upvoted 0 times
...
Sage
12 months ago
This seems pretty straightforward. I'd focus on reviewing the contract details and interviewing the relevant parties to understand the billing issues.
upvoted 0 times
...
Kiley
12 months ago
I've seen questions like this before. The key is to pay attention to the details and understand the implications of the code. I'm feeling pretty confident about this one.
upvoted 0 times
...
Mirta
12 months ago
Business plans should be agile, that's the whole point. This has to be true.
upvoted 0 times
...

Save Cancel